# Webber, LLC: TxDOT widen freeway contract 100%+ complete, IH 37, San Patricio County ($92,020,740, 21 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Webber, LLC |
| Subcontractors | Highway Barricades And Services, LLC (0.79%); A Brothers Milling, LLC (0.24%); Adcock 4 Investments, LLC (1.66%); Creacom, INC. (5.1%); Gp7 Construction INC. (2.83%); Highway Pavement Specialties, INC. (0.07%); Scott Derr Painting Co, LLC (0.13%); Bay LTD. (9.71%); A. H. Beck Foundation Co., INC. (5.86%); Frank Jr Reinforcement LLC (0.52%); Texas Steel Industrial Placing, LLC (2.4%); Martin Marietta Materials, INC. (1.18%); Brazos River Contractors LLC (2.62%); Sk Concrete Services LLC (0.1%); Terra Construction LLC (0.07%); 4e Infra Construction LLC (0.45%); Aggregate Technologies, INC. (0.16%); Soil Tech Advance INC. (0.1%); Scr Civil Construction, LLC (0.14%); Mtam Corporation (0.08%); Panther Creek Transportation, INC. (0.94%) |
| Progress | 101.47% complete, 84.38% of time used |
| Amount | $92,020,740 revised (original $83,990,747) |
| Change orders | $6,305,859 |
| Paid to date | $91,623,460 |
| Work | Widen Freeway |
| Location | IH 37, NUECES RIVER (CB) to IH37/US 77 INTERCHANGE, San Patricio County, Corpus Christi District |
| Let / began | 2021-05-05 / 2021-09-20 |
| Latest estimate | 2026-10-02 |
| Contract number | 5213001 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.