# Webber, LLC: TxDOT newlocation non-freeway contract 78% complete, SH 84, Webb County ($122,673,213, 15 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Webber, LLC |
| Subcontractors | Toro Bravo Construction, LLC (1.63%); Sk Concrete Services LLC (0.08%); Highway Barricades And Services, LLC (0.3%); Texas Materials Group, INC. (6.89%); Rc Contract Services LLC (1.02%); Uvalle & Sons Trucking LLC (0%); Soliz Paving, INC. (4.39%); Tri County Construction (1.15%); A Brothers Milling, LLC (0.05%); D&G Energy Corporation (1.54%); Laredo Striping, INC. (0.07%); South Texas Traffic Alliance INC. (0.03%); Terra Construction LLC (2.54%); Texas Environmental Management - San Antonio, INC. (1.15%); Royal E Construction, LLC (0.27%) |
| Progress | 78.41% complete, 64.39% of time used |
| Amount | $122,673,213 revised (original $122,229,769) |
| Change orders | $443,444 |
| Paid to date | $96,192,333 |
| Work | Newlocation Non-Freeway |
| Location | SH 84, FM 1472 to IH 35 WEST FRONTAGE ROAD, Webb County, Laredo District |
| Let / began | 2024-05-02 / 2024-08-12 |
| Latest estimate | 2026-10-05 |
| Contract number | 5243002 |

## Why this score
- Contract over $10M.