# Webber, LLC: TxDOT widen freeway contract 96% complete, US 80, Kaufman County ($124,239,117, 29 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Webber, LLC |
| Subcontractors | Hb Farmer Foundation, LLC (4.72%); J. H. Oden Contracting Company (0.54%); Je Casey, LLC (0.31%); Toro Bravo Construction, LLC (5.85%); Tex Op Construction, LP (0.2%); Texas Materials Group, INC. (9.92%); Mica Corporation (2.41%); Houston Sawing & Drilling (0.1%); Dustin Allen, INC. (0.17%); 190 Construction LLC (1.71%); Straight Line Sawing & Sealing, INC. (0.01%); J & M Contracting, Company (1.5%); Traffic Highway Maintenance, LLC (0.25%); Pannell Industries, INC. (0.02%); Indus Road & Bridge, INC. (1.06%); H Services, LLC (0.04%); Durable Specialties, INC. (0.45%); Avanza Construction & Earthworks, LLC (1.79%); Monarrez Trucking LLC. (0.16%); Green Source Environmental Solutions, INC. (0.06%); Vista Ridge Concrete Pumping, INC. (0.18%); Cnd Contracting, LLC (0.61%); Q. Roberts Trucking Incorporated (2.36%); A-Core Concrete Cutting, INC. (0.01%); Mtam Corporation (0.03%); Elite Striping, LLC (0.02%); J.H. Painting Company (0.16%); Stripe-A-Zone, LLC (0.14%); Nortex Concrete Lift & Stabilization, INC. (0.04%) |
| Progress | 96.24% complete, 101.96% of time used |
| Amount | $124,239,117 revised (original $119,542,801) |
| Change orders | $707,680 |
| Paid to date | $115,732,699 |
| Work | Widen Freeway |
| Location | US 80, LAWSON RD (DALLAS / KAUFMAN C/L) to FM 460, Kaufman County, Dallas District |
| Let / began | 2022-06-29 / 2023-04-03 |
| Latest estimate | 2026-10-02 |
| Contract number | 6223401 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.