# Webber, LLC: TxDOT widen non-freeway contract 100%+ complete, SH 46, Comal County ($61,541,240, 19 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Webber, LLC |
| Subcontractors | Geosource, INC. (0.08%); Adcock 4 Investments, LLC (4.32%); Lone Star Paving Company (19.19%); Roadway Specialties, INC. (0.89%); Flasher Equipment Company (0.86%); Wampole Miller, INC. (2.98%); The Levy Company, INC. (5.16%); Rucoba & Maya Construction, LLC (0.88%); Scott Derr Painting Co, LLC (0.04%); Badger Daylighting Corp. (0.02%); H. L. Chapman Pipeline Construction, INC. (0.41%); Sk Concrete Services LLC (0.01%); Mtam Corporation (0.03%); Jt Underground And Utility Construction INC (0%); Rio Grande Rebar Rodbusters, LLC (0%); Toro Bravo Construction, LLC (0.14%); Curb Planet INC. (0.14%); Fibertel, LLC (0.09%); Panther Creek Transportation, INC. (3.9%) |
| Progress | 106.84% complete, 99.77% of time used |
| Amount | $61,541,240 revised (original $59,488,630) |
| Change orders | $2,052,610 |
| Paid to date | $65,748,757 |
| Work | Widen Non-Freeway |
| Location | SH 46, US 281 to BENTWOOD DR., Comal County, San Antonio District |
| Let / began | 2022-06-30 / 2022-10-10 |
| Latest estimate | 2026-10-05 |
| Contract number | 6223607 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.