# Webber, LLC: TxDOT convert non-freeway to freeway contract 61% complete, US 59, San Jacinto County ($192,491,946, 26 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Webber, LLC |
| Subcontractors | J & D Tex Serv, Incorporated (1.88%); Creacom, INC. (0.17%); Aggregate Technologies, INC. (0.01%); Jbc Consolidated, LLC (1.01%); (Inactive)mesa Rod Busters, INC. (1.72%); King George Traffic Solutions LLC (0.9%); Lonestar Traffic Safety, LLC (0.08%); Rdi Foundation Drilling (3.85%); Willow City Sign & Rail, INC. (0.35%); Antigo Construction, INC. (0.11%); Gmj Paving Co. (5.8%); Mbn Enterprises LLC (0.52%); Mtam Corporation (0.07%); Primate Construction, LP (0.05%); Professional Traffic Control LLC (0%); Scott Derr Painting Co, LLC (0.03%); Sk Concrete Services LLC (0.21%); J. H. Oden Contracting Company (0.14%); Bella Paving, INC. (0.34%); Jam Materials, LLC (0.19%); Tex Op Construction, LP (0.69%); Cnd Contracting, LLC (0.03%); Thomas Tractor Works, INC. (0.2%); Valley Placers, LLC (0.19%); Third Coast Services LLC (2.46%); Durwood Greene Construction Co. (5.8%) |
| Progress | 61.24% complete, 55.39% of time used |
| Amount | $192,491,946 revised (original $189,820,654) |
| Change orders | $2,159,292 |
| Paid to date | $117,561,792 |
| Work | Convert Non-Freeway To Freeway |
| Location | US 59, FM 2914 to LIBERTY C/L, San Jacinto County, Lufkin District |
| Let / began | 2023-06-27 / 2023-12-14 |
| Latest estimate | 2026-10-05 |
| Contract number | 6233402 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.