# Webber, LLC: TxDOT hazard elimination & safety contract 100%+ complete, US 75, Collin County ($61,140,287, 19 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Webber, LLC |
| Subcontractors | Breda Company, INC. (0%); Adrian Contracting, INC (0.31%); Redline Construction Services LLC (0.94%); USA Swppp Inspections, INC. (0.4%); J.H. Painting Company (0.37%); Hermanos Steel, LLC (0.22%); USA Amtech, INC. (1.45%); Monarrez Trucking LLC. (1.19%); Stripe-A-Zone, LLC (2.21%); Traffic Highway Maintenance, LLC (1.35%); Pannell Industries, INC. (0.13%); Act Saw Cutting & Removal (0.05%); Next Generation Construction & Environmental, LLC (0.47%); Mica Corporation (37.02%); Southern Cross Contractors, LLC (1.24%); Surface Preparation Technologies, LLC (0.14%); Fc Traffic Control, INC. (0.1%); Sweeping Corporation Of America, LLC (0.12%); Redland Constrcution LLC (0%) |
| Progress | 102.55% complete, 93.21% of time used |
| Amount | $61,140,287 revised (original $58,488,663) |
| Change orders | $1,373,824 |
| Paid to date | $61,388,498 |
| Work | Hazard Elimination & Safety |
| Location | US 75, IH 635 to SH 121, Collin County, Dallas District |
| Let / began | 2023-08-03 / 2024-03-04 |
| Latest estimate | 2026-10-05 |
| Contract number | 8233203 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.