# Westfield Insurance Company: TxDOT bridge replacement contract 36% complete, FM 731, Johnson County ($3,591,524, 18 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Westfield Insurance Company |
| Subcontractors | Firmitas Construction LLC (34.49%); Stoic Civil Construction, INC. (12.59%); Tucan Contracting, LLC (25.91%); Southern Cross Contractors, LLC (1.61%); Foutsco Paving Company, LLC (99.58%); Linear Traffic Markings LLC (1.2%); USA Swppp Inspections, INC. (1.33%); Legacy Construction Management Services, LLC (62.63%); Farr Foundation, INC. (3.15%); Civil Tree Solutions, LLC (0.66%); Lindamood, INC. (0.84%); Beaird Drilling Services, INC. (3.82%); K&A Rebar & Post-Tension LLC (0.13%); Trp Construction Group, LLC (0.72%); Tex Op Construction, LP (0.37%); Diibs Specialists, LLC (0.79%); Peachtree Construction, LTD. (5.87%); Jamesboy, LLC (5.47%) |
| Progress | 35.88% complete, 74.91% of time used |
| Amount | $3,591,524 revised (original $3,569,154) |
| Change orders | $22,157 |
| Paid to date | $1,288,438 |
| Work | Bridge Replacement |
| Location | FM 731, AT VILLAGE CREEK to ., Johnson County, Fort Worth District |
| Let / began | 2025-03-05 / 2025-09-29 |
| Latest estimate | 2026-10-06 |
| Contract number | 3253219 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.