# Westfield Insurance Company: TxDOT bridge replacement contract 57% complete, SH 176, Howard County ($2,537,007, 12 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Westfield Insurance Company |
| Subcontractors | Fc Traffic Control, INC. (2.28%); Tucan Contracting, LLC (22.18%); Davis Motor Crane Service, INC. (1.85%); Gregory Pile Driving, INC. (9.44%); Hjc Farms, INC. (6.34%); Professional Traffic Control LLC (0.44%); Trp Construction Group, LLC (0.86%); Texop Construction (0.89%); Toro Bravo Construction, LLC (2.24%); Ace's Welding & Fabrication LLC (4.96%); J. H. Strain & Sons, INC. (9.71%); Skyline Bridge LLC (76.81%) |
| Progress | 57.06% complete, 119.57% of time used |
| Amount | $2,537,007 revised (original $2,389,848) |
| Change orders | $144,159 |
| Paid to date | $1,445,864 |
| Work | Bridge Replacement |
| Location | SH 176, AT SULPHUR SPRINGS DRAW to ., Howard County, Abilene District |
| Let / began | 2024-06-06 / 2024-09-30 |
| Latest estimate | 2026-10-06 |
| Contract number | 6243237 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.