# Westfield Insurance Company: TxDOT bridge replacement contract 58% complete, CS, Parker County ($1,528,864, 10 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Westfield Insurance Company |
| Subcontractors | Hilbash Investment LLC (40.27%); Fortson Contracting, INC. (0%); Tex Op Construction, LP (0%); Trp Construction Group, LLC (0%); Texas Shafts, INC. (10.17%); Wolfe Construction Group, Incorporated (1.25%); Southeast Grinding And Grooving LLC (0.39%); Toro Bravo Construction, LLC (0%); Hermanos Steel, LLC (0%); Prater Dirt Work LLC (0%) |
| Progress | 57.93% complete, 117.05% of time used |
| Amount | $1,528,864 revised (original $1,536,599) |
| Change orders | $-7,741 |
| Paid to date | $885,730 |
| Work | Bridge Replacement |
| Location | CS, KINGS GATE to @ CLEAR FORK TRINITY RIVER, Parker County, Fort Worth District |
| Let / began | 2025-08-08 / 2025-11-10 |
| Latest estimate | 2026-10-06 |
| Contract number | 8253215 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.