# Wg Engineering & Construction, LLC: TxDOT maintenance contract 22% complete, IH0020, Tarrant County ($2,460,054, 1 sub)

**Score:** 60/100

| Field | Value |
|---|---|
| Prime contractor | Wg Engineering & Construction, LLC |
| Subcontractors | Roadmaster, INC. (0%) |
| Progress | 21.87% complete, 51.37% of time used |
| Amount | $2,460,054 revised (original $2,385,405) |
| Change orders | $74,617 |
| Paid to date | $538,018 |
| Work | Maintenance |
| Location | IH0020, VARIOUS LOCATIONS IN to FT WORTH DISTRICT, Tarrant County, Fort Worth District |
| Let / began | 2025-05-01 / 2025-09-16 |
| Latest estimate | 2026-09-30 |
| Contract number | 5254002 |

## Why this score
- Contract over $1M.
- Under 25% complete: most materials and sub work still ahead.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.