# Wg Engineering & Construction, LLC: TxDOT traffic signal contract 73% complete, SL 12, Dallas County ($4,237,243, 3 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Wg Engineering & Construction, LLC |
| Subcontractors | Jr West Texas Concrete LLC (17.8%); Road Master Striping, LLC (2.69%); Blue Rock Utilities LLC (2.49%) |
| Progress | 73.09% complete, 70.83% of time used |
| Amount | $4,237,243 revised (original $4,223,543) |
| Paid to date | $3,087,074 |
| Work | Traffic Signal |
| Location | SL 12, VARIOUS INTERSECTIONS to IN THE CITY OF DALLAS, Dallas County, Dallas District |
| Let / began | 2025-06-04 |
| Latest estimate | 2026-10-01 |
| Contract number | 6253021 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.