# Williams Brothers Construction Co., INC.: TxDOT widen freeway contract 82% complete, IH 30, Rockwall County ($318,242,202, 28 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Williams Brothers Construction Co., INC. |
| Subcontractors | Sal's Treescape Service INC (0%); Imt Construction, LLC (0.09%); Trp Construction Group, LLC (0.26%); Toro Bravo Construction, LLC (0.42%); Wims Environmental Construction, LTD. (0.56%); Highway Pavement Specialties, INC. (0.12%); North Texas Contracting, INC. (3.49%); Texas Materials Group, INC. (2.67%); (Inactive)royal Rebar (0.93%); Scott Derr Painting Co, LLC (0.04%); Structural Technologies, LLC (0.09%); Highway Intelligent Traffic Solutions, LLC (1.92%); Ats Drilling, INC. (13.01%); Act Saw Cutting & Removal (0.08%); Pannell Industries, INC. (0.2%); Southwest Road & Safety Contractors, LTD. (0.79%); Buyers Barricades, INC. (0.01%); Hall Right Of Way Services, LLC (0.09%); A R Daniel Construction Services, Incorporated (0.22%); Sweeping Corporation Of America, LLC (0.14%); Mpire Industries Commercial Diving Services LLC (0.06%); Martinus Bottom Line, LLC (0.04%); Traffic Tech Solutions, LLC (0%); Sk Concrete Services LLC (0.07%); Hart Services LLC (0%); Hb Farmer Foundation, LLC (0.13%); Blue Rock Drilling, LLC (0%); A-Core Concrete Cutting Of Texas, INC. (0%) |
| Progress | 82.16% complete, 90.18% of time used |
| Amount | $318,242,202 revised (original $312,522,588) |
| Change orders | $927,215 |
| Paid to date | $257,539,298 |
| Work | Widen Freeway |
| Location | IH 30, DALROCK RD (DALLAS C/L) to SH 205, Rockwall County, Dallas District |
| Let / began | 2022-10-07 / 2023-03-27 |
| Latest estimate | 2026-10-02 |
| Contract number | 10223201 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.