# Williams Brothers Construction Co., INC.: TxDOT interchange (new or reconstructed) contract 42% complete, IH 30, Hunt County ($197,966,061, 18 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Williams Brothers Construction Co., INC. |
| Subcontractors | Reynolds Asphalt & Construction Company (16.17%); Peachtree Construction, LTD. (1.13%); Highway Intelligent Traffic Solutions, LLC (0.78%); (Inactive)royal Rebar (2.6%); Buyers Barricades, INC. (0.02%); Wims Environmental Construction, LTD. (0.51%); Wylie Drilling & Drainage, INC. (0.39%); King George Traffic Solutions LLC (0.76%); North Texas Contracting, INC. (8.67%); Sk Concrete Services LLC (0.1%); Cell-Crete Corporation (0%); Roadway Specialties, INC. (1.37%); Sal's Treescape Service INC (0.02%); Texana Land & Asphalt, INC. (0%); Act Saw Cutting & Removal (0%); Imt Construction, LLC (0%); Striping Technology, L.P. (0.82%); Southwest Road & Safety Contractors, LTD. (0.62%) |
| Progress | 42.02% complete, 55.92% of time used |
| Amount | $197,966,061 revised (original $188,468,889) |
| Change orders | $7,591,903 |
| Paid to date | $82,394,370 |
| Work | Interchange (New Or Reconstructed) |
| Location | IH 30, IH 30 FROM .75 MILES WEST CR 2509 TO 1.0 MILES EAST OF FM 36, Hunt County, Paris District |
| Let / began | 2023-10-06 / 2024-03-11 |
| Latest estimate | 2026-10-05 |
| Contract number | 10233201 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.