# Williams Brothers Construction Co., INC.: TxDOT interchange (new or reconstructed) contract 100% complete, IH 30, Tarrant County ($331,282,906, 42 subs)

**Score:** 75/100

| Field | Value |
|---|---|
| Prime contractor | Williams Brothers Construction Co., INC. |
| Subcontractors | (Inactive)under Construction INC. (0.06%); Foundation Drillers, INC. (0.02%); Morning Star Tree Service (0%); Roadway Construction, INC. (0.01%); N.L. Schutte Foundation Drilling, INC. (0.03%); Prime Utility Construction, L.L.C. (0.01%); (Inactive)imt Construction, LLC (0.01%); Reliable Concrete Cutting LLC (0%); Dallas Foundation Drilling Co., INC. (0.02%); A R Daniel Construction Services, Incorporated (0.02%); Ray's Threading And Fab Shop (0.14%); Circle H Contractors, L.P. (0.01%); Sweeping Services Of Texas - Operating, L.P. (0.07%); M W Panel Tech, LLC (0.4%); Highway Intelligent Traffic Solutions, LLC (0.01%); Southwest Road & Safety Contractors, LTD. (0.23%); North Texas Intelligent Transportation Systems LLC (0.04%); Cell-Crete Corporation (0.08%); Infinity Lawn & Landscape, LLC (0.37%); Nortex Concrete Lift & Stabilization, INC. (0.01%); A-Core Concrete Cutting Of Texas, INC. (0%); Straight Line Sawing & Sealing, INC. (0%); Collier Services LLC (0.39%); Mike Albert, INC. (0.1%); (Inactive)priority Environmental Services, INC. (0.28%); Bore Company, LLC (0.21%); Excel 4 Construction, LLC (0.07%); Jagoe-Public Company (0.1%); Buyers Barricades, INC. (0%); USA Swppp Inspections, INC. (0.71%); Thelin Recycling Company, L.P. (0.04%); (Inactive)total Highway Maintenance, LLC (0.42%); (Inactive)royal Rebar (3.85%); Ark Contracting Services, LLC (1.64%); Integrated Roadway Services, INC. (3.13%); Scott Derr Painting Co, LLC (0.15%); Highway Pavement Specialties, INC. (0.05%); F A Brown's Construction, LLC (0.48%); Reynolds Asphalt & Construction Company (4.05%); W.O.E. Construction, INC. (2.37%); (Inactive)ar Daniel Construction Services, INC. (0.06%); North Texas Contracting, INC. (5.17%) |
| Progress | 99.56% complete, 99.43% of time used |
| Amount | $331,282,906 revised (original $233,181,889) |
| Change orders | $96,451,671 |
| Paid to date | $328,188,990 |
| Work | Interchange (New Or Reconstructed) |
| Location | IH 30, 1.0 MI W OF SH 360 to GREAT SOUTHWEST PKWY, Tarrant County, Fort Worth District |
| Let / began | 2015-11-04 / 2016-01-19 |
| Latest estimate | 2026-10-06 |
| Contract number | 11153231 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.