# Williams Brothers Construction Co., INC.: TxDOT upgrade to standards non-freeway contract 52% complete, US 59, Wharton County ($345,189,438, 20 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Williams Brothers Construction Co., INC. |
| Subcontractors | A. H. Beck Foundation Co., INC. (3.72%); Base Construction L.L.P. (5.4%); Buyers Barricades, INC. (0%); Freyssinet, INC. (0.25%); J. H. Oden Contracting Company (0.27%); James Construction Group, LLC (4.62%); Long Legacy Enterprises, LLC (0.02%); (Inactive)paveloc Industries LLC (0.12%); Buyers Barricades Houston, LLC (0.19%); Scott Derr Painting Co, LLC (0.02%); Sk Concrete Services LLC (0.21%); Southwest Road & Safety Contractors, LTD. (0.54%); Sweeping Corporation Of America, LLC (0.05%); Allstate Signal & Construction, LLC (3.74%); (Inactive)mesa Rod Busters, INC. (2.02%); Roadway Construction, INC. (0.07%); Trp Construction Group, LLC (0.44%); Durwood Greene Construction Co. (4.62%); Roy Jorgensen Associates, INC. (0.04%); Doran Steel, INC. (0.28%) |
| Progress | 52.3% complete, 45.55% of time used |
| Amount | $345,189,438 revised (original $342,707,535) |
| Change orders | $-562,111 |
| Paid to date | $178,941,289 |
| Work | Upgrade To Standards Non-Freeway |
| Location | US 59, 0.26 MI. NORTH OF FM 102 to 1 MI SOUTH OF FM 961, Wharton County, Yoakum District |
| Let / began | 2023-12-06 / 2024-01-18 |
| Latest estimate | 2026-10-05 |
| Contract number | 12233201 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.