# Williams Brothers Construction Co., INC.: TxDOT restoration contract 23% complete, IH 35, Bexar County ($222,430,680, 14 subs)

**Score:** 75/100

| Field | Value |
|---|---|
| Prime contractor | Williams Brothers Construction Co., INC. |
| Subcontractors | Southwest Road & Safety Contractors, LTD. (0.65%); Sk Concrete Services LLC (0.14%); Z & L Concrete Contractors, INC. (4.31%); Royal Rebar INC (1.46%); Trp Construction Group, LLC (0.53%); Buyers Barricades San Antonio, LLC (0.21%); The Levy Company, INC. (5.42%); A R Daniel Construction Services, Incorporated (0.08%); Clear Restoration, LLC (0.13%); Scott Derr Painting Co, LLC (0.05%); Taylor Bridge LLC (1.03%); Mccall Drilling Hdd INC (0.41%); Cherokee Services (0.03%); Badeco, INC. (0.17%) |
| Progress | 23.44% complete, 14.2% of time used |
| Amount | $222,430,680 revised (original $221,480,420) |
| Change orders | $950,260 |
| Paid to date | $52,128,580 |
| Work | Restoration |
| Location | IH 35, N. WALTERS ST. to IH 410 S, Bexar County, San Antonio District |
| Let / began | 2025-12-03 |
| Latest estimate | 2026-10-06 |
| Contract number | 12253201 |

## Why this score
- Contract over $10M.
- Under 25% complete: most materials and sub work still ahead.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.