# Williams Brothers Construction Co., INC.: TxDOT widen freeway contract 54% complete, IH 10, Jefferson County ($315,542,678, 20 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Williams Brothers Construction Co., INC. |
| Subcontractors | Sweeping Services Of Texas - Operating, L.P. (0.02%); Buyers Barricades Houston, LLC (0.16%); American Remediation Options, INC. (0.22%); Texas Environmental Management - San Antonio, INC. (0.63%); Allstate Signal & Construction, LLC (2.8%); (Inactive)royal Rebar (9.26%); Southwest Road & Safety Contractors, LTD. (0.17%); Highway Pavement Specialties, INC. (0.12%); Scott Derr Painting Co, LLC (0.09%); Batterson, LLP (0.51%); West Texas Rock Resources, LLC (0.02%); A R Daniel Construction Services, Incorporated (1.58%); Long Legacy Enterprises, LLC (0.05%); Base Construction L.L.P. (0.76%); Superior Grouting Services, INC. (0%); Sk Concrete Services LLC (0.24%); Texas Materials Group, INC. (0.03%); Batten Drilling, INC. (0.24%); Skidabrader Group LLC (0.01%); O. Trevino Construction, LLC (0.21%) |
| Progress | 53.55% complete, 54.45% of time used |
| Amount | $315,542,678 revised (original $307,243,558) |
| Change orders | $8,299,120 |
| Paid to date | $168,969,570 |
| Work | Widen Freeway |
| Location | IH 10, CR 131 (WALDEN ROAD), EAST to US 90, Jefferson County, Beaumont District |
| Let / began | 2022-03-03 / 2022-04-14 |
| Latest estimate | 2026-10-02 |
| Contract number | 3223001 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.