# Williams Brothers Construction Co., INC.: TxDOT widen freeway contract 100%+ complete, SL 1604, Bexar County ($154,425,589, 27 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Williams Brothers Construction Co., INC. |
| Subcontractors | The Levy Company, INC. (5.91%); Eggemeyer Land Clearing, LLC (0.05%); Flasher Equipment Company (0.63%); (Inactive)royal Rebar (2.24%); American Signal Equipment Co., INC. (Converse) (0.17%); Badeco, INC. (2.28%); Z & L Concrete Contractors, INC. (4.53%); Texas Environmental Management - San Antonio, INC. (0.19%); Dywidag-Systems International_usa,INC. (0.1%); Roadway Construction, INC. (3.1%); Roadway Specialties, INC. (0.13%); Highway Pavement Specialties, INC. (0.12%); Scott Derr Painting Co, LLC (0.05%); Rio Grande Rebar Rodbusters, LLC (0%); Light It Up Electric (0%); Dakota Utility Contractors, INC. (0%); Jt Underground And Utility Construction INC (0%); Fibertel, LLC (0%); A. H. Beck Foundation Co., INC. (0%); Structural Integrity Group LLC (0.04%); Harris Hardrock Trenching, L.L.C. (0%); H. L. Chapman Pipeline Construction, INC. (0.16%); Superior Grouting Services, INC. (0%); Mpr Services (0.09%); Sk Concrete Services LLC (0.22%); Sweeping Corporation Of America, LLC (0.02%); Highway Barricades And Services, LLC (0%) |
| Progress | 100.02% complete, 100% of time used |
| Amount | $154,425,589 revised (original $148,073,104) |
| Change orders | $6,352,485 |
| Paid to date | $154,454,533 |
| Work | Widen Freeway |
| Location | SL 1604, SH 16 to IH 10, Bexar County, San Antonio District |
| Let / began | 2021-04-07 / 2021-05-10 |
| Latest estimate | 2026-10-05 |
| Contract number | 4213001 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.