# Williams Brothers Construction Co., INC.: TxDOT widen freeway contract 37% complete, IH 10, Jefferson County ($543,815,681, 16 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Williams Brothers Construction Co., INC. |
| Subcontractors | Sweeping Corporation Of America, LLC (0.02%); Texas Materials Group, INC. (0.01%); Allstate Signal & Construction, LLC (2.34%); American Remediation Options, INC. (0.35%); (Inactive)royal Rebar (4.11%); Buyers Barricades Houston, LLC (0.15%); Southwest Road & Safety Contractors, LTD. (0.09%); A R Daniel Construction Services, Incorporated (0.42%); Uretek USA, INC. (0.01%); Sk Concrete Services LLC (0.1%); Scott Derr Painting Co, LLC (0%); Trp Construction Group, LLC (0.44%); O. Trevino Construction, LLC (0.12%); Skidabrader Group LLC (0.07%); Kay Services, INC. (0.01%); Batten Drilling, INC. (0.12%) |
| Progress | 37.31% complete, 21.11% of time used |
| Amount | $543,815,681 revised (original $533,247,313) |
| Change orders | $10,568,368 |
| Paid to date | $202,904,168 |
| Work | Widen Freeway |
| Location | IH 10, HOLLYWOOD OVERPASS, EAST to 7TH STREET, Jefferson County, Beaumont District |
| Let / began | 2024-05-02 / 2024-07-10 |
| Latest estimate | 2026-10-02 |
| Contract number | 5243001 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.