# Williams Brothers Construction Co., INC.: TxDOT miscellaneous construction contract 83% complete, IH 45, Galveston County ($251,207,443, 20 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Williams Brothers Construction Co., INC. |
| Subcontractors | Cen-Tex Irrigation Systems, INC. (0.2%); (Inactive)base Construction (9.66%); (Inactive)hayward Baker, INC. (0.3%); Highway Pavement Specialties, INC. (0.16%); (Inactive)mesa Rod Busters, INC. (7.45%); Texas Environmental Management - San Antonio, INC. (0.63%); Professional Traffic Control LLC (0.57%); Scott Derr Painting Co, LLC (0.03%); Southwest Road & Safety Contractors, LTD. (0.4%); Traffic Systems Construction, INC. (3.73%); Ray's Threading And Fab Shop (0.6%); Online Directional Boring, LP (0.02%); Base Construction L.L.P. (0.76%); Bortunco (0.1%); Ashton Sawing And Drilling LLC (0%); Cpave, INC. (0.01%); Long Legacy Enterprises, LLC (0.01%); Keller North America, INC. (0%); Sk Concrete Services LLC (0.22%); Roadway Construction, INC. (0.21%) |
| Progress | 82.63% complete, 98.67% of time used |
| Amount | $251,207,443 revised (original $230,477,521) |
| Change orders | $19,249,923 |
| Paid to date | $206,354,261 |
| Work | Miscellaneous Construction |
| Location | IH 45, N OF FM 517 to S OF FM 1764, Galveston County, Houston District |
| Let / began | 2018-06-05 / 2018-07-26 |
| Latest estimate | 2026-09-30 |
| Contract number | 6183001 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.