# Williams Brothers Construction Co., INC.: TxDOT widen freeway contract 99% complete, IH 10, Orange County ($58,360,157, 17 subs)

**Score:** 75/100

| Field | Value |
|---|---|
| Prime contractor | Williams Brothers Construction Co., INC. |
| Subcontractors | (Inactive)mesa Rod Busters, INC. (1.18%); Highway Pavement Specialties, INC. (0.23%); Area Wide Protective, INC. (0.38%); A R Daniel Construction Services, Incorporated (1.74%); Southwest Road & Safety Contractors, LTD. (0.75%); Allstate Signal & Construction, LLC (5.94%); American Remediation Options, INC. (0.4%); Scott Derr Painting Co, LLC (0.03%); (Inactive)total Highway Maintenance, LLC (1.3%); Adcock 4 Investments, LLC (0.57%); Ray's Threading And Fab Shop (0.59%); Long Legacy Enterprises, LLC (0.01%); Sweeping Services Of Texas - Operating, L.P. (0.2%); Texas Materials Group, INC. (0.06%); Sk Concrete Services LLC (0.33%); Batten Drilling, INC. (0.49%); A-Core Concrete Cutting Of Texas, INC. (0.01%) |
| Progress | 98.75% complete, 99.37% of time used |
| Amount | $58,360,157 revised (original $52,363,934) |
| Change orders | $5,996,223 |
| Paid to date | $57,628,351 |
| Work | Widen Freeway |
| Location | IH 10, 0.54 MILES EAST OF FM 3247 to SABINE RIVER BRIDGE, Orange County, Beaumont District |
| Let / began | 2020-06-05 / 2020-09-16 |
| Latest estimate | 2026-10-02 |
| Contract number | 6203204 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.