# Williams Brothers Construction Co., INC.: TxDOT widen freeway contract 78% complete, IH 10, Bexar County ($420,223,347, 24 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Williams Brothers Construction Co., INC. |
| Subcontractors | Sweeping Services Of Texas - Operating, L.P. (0.04%); Z & L Concrete Contractors, INC. (2.74%); Light It Up Electric (0%); Jt Underground And Utility Construction INC (0%); Mpr Services (0.06%); Hdw Construction & Drilling, LLC. (0%); M&M Directional Drilling, LLC (0%); Keller North America, INC. (0.07%); Roadway Construction, INC. (0.07%); Sk Concrete Services LLC (0.21%); Dakota Utility Contractors, INC. (0%); Scott Derr Painting Co, LLC (0%); Fibertel, LLC (0%); J.A. Road Boring, INC. (0%); Rio Grande Rebar Rodbusters, LLC (0%); Badeco, INC. (1.05%); Buyers Barricades San Antonio, LLC (0.14%); D Guerra Construction LLC (1.64%); Flasher Equipment Company (0.57%); Highway Pavement Specialties, INC. (0.12%); H. L. Chapman Pipeline Construction, INC. (0.24%); J. H. Oden Contracting Company (0.09%); (Inactive)royal Rebar (5.36%); The Levy Company, INC. (3.82%) |
| Progress | 78.31% complete, 81.92% of time used |
| Amount | $420,223,347 revised (original $418,111,026) |
| Change orders | $2,112,320 |
| Paid to date | $329,069,137 |
| Work | Widen Freeway |
| Location | IH 10, AT LP 1604 NORTH to ., Bexar County, San Antonio District |
| Let / began | 2022-06-01 / 2022-07-13 |
| Latest estimate | 2026-10-05 |
| Contract number | 6223001 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.