# Williams Brothers Construction Co., INC.: TxDOT widen freeway contract 89% complete, IH 45, Galveston County ($172,993,517, 17 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Williams Brothers Construction Co., INC. |
| Subcontractors | Bortunco (0.76%); Base Construction L.L.P. (13.8%); Texas Environmental Management - San Antonio, INC. (0.41%); Highway Pavement Specialties, INC. (0.14%); Scott Derr Painting Co, LLC (0.02%); A & A Construction (0.28%); A&J Rebar LLC (2.51%); Southwest Road & Safety Contractors, LTD. (0.59%); Traffic Systems Construction, INC. (3.98%); Ray's Threading And Fab Shop (0.5%); Roadway Construction, INC. (0.21%); Professional Traffic Control LLC (0.65%); A & A Construction Company (0.28%); Sweeping Corporation Of America, LLC (0.05%); Highway 1 LLC (0.01%); Sk Concrete Services LLC (0.25%); Trp Construction Group, LLC (0.01%) |
| Progress | 88.78% complete, 111.2% of time used |
| Amount | $172,993,517 revised (original $165,825,007) |
| Change orders | $5,413,510 |
| Paid to date | $152,030,378 |
| Work | Widen Freeway |
| Location | IH 45, SOUTH OF FM 1764 to NORTH OF FM 519, Galveston County, Houston District |
| Let / began | 2019-08-07 / 2019-09-23 |
| Latest estimate | 2026-09-30 |
| Contract number | 8193201 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.