# Williams Brothers Construction Co., INC.: TxDOT widen freeway contract 66% complete, IH 45, Galveston County ($114,624,116, 14 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Williams Brothers Construction Co., INC. |
| Subcontractors | Sweeping Services Of Texas - Operating, L.P. (0.04%); Pavement Markings INC. (0%); Southwest Road & Safety Contractors, LTD. (0.66%); Highway Pavement Specialties, INC. (0.12%); Quality Turf Farms, L.C. (0.49%); Allstate Signal & Construction, LLC (2.08%); Base Construction L.L.P. (5.14%); Scott Derr Painting Co, LLC (0.03%); (Inactive)royal Rebar (7.77%); Pmi Pavement Marking, LLC (0.53%); Batterson, LLP (0.52%); Highway 1 LLC (0%); Sk Concrete Services LLC (0.31%); Trp Construction Group, LLC (0.01%) |
| Progress | 65.85% complete, 71.58% of time used |
| Amount | $114,624,116 revised (original $103,251,457) |
| Change orders | $8,347,658 |
| Paid to date | $73,491,163 |
| Work | Widen Freeway |
| Location | IH 45, S OF TEXAS CITY WYE to N OF CAUSEWAY, Galveston County, Houston District |
| Let / began | 2020-08-06 / 2020-10-21 |
| Latest estimate | 2026-09-30 |
| Contract number | 8203202 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.