# Williams Brothers Construction Co., INC.: TxDOT widen freeway contract 73% complete, IH 45, Walker County ($229,969,145, 22 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Williams Brothers Construction Co., INC. |
| Subcontractors | (Inactive)mesa Rod Busters, INC. (0%); Long Legacy Enterprises, LLC (0.02%); Wims Environmental Construction, LTD. (0.73%); West Texas Rock Resources, LLC (0%); Highway 1 LLC (0.54%); Allstate Signal & Construction, LLC (2.63%); Southwest Road & Safety Contractors, LTD. (0.55%); Buyers Barricades Houston, LLC (0.16%); Base Construction L.L.P. (12.09%); Big Creek Construction, LTD. (6.43%); Structural Integrity Group LLC (0.11%); Highway Pavement Specialties, INC. (0.12%); Scott Derr Painting Co, LLC (0.51%); Speedy Paving (0.1%); Encino Landscape, INC. (1.42%); Bortunco (0.08%); Curb Planet INC. (0.12%); Roadway Construction, INC. (0.12%); Batten Drilling, INC. (0.15%); Mesa Rod Busters INC (4.1%); Trp Construction Group, LLC (0.46%); Sk Concrete Services LLC (0.25%) |
| Progress | 73.36% complete, 81.75% of time used |
| Amount | $229,969,145 revised (original $198,146,415) |
| Change orders | $21,278,366 |
| Paid to date | $160,971,975 |
| Work | Widen Freeway |
| Location | IH 45, 0.3 MILES NORTH OF SH 19 to SH 30, Walker County, Bryan District |
| Let / began | 2021-09-02 / 2021-10-18 |
| Latest estimate | 2026-10-05 |
| Contract number | 9213201 |

## Why this score
- Contract over $10M.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.