# Williams Brothers Construction Co., INC.: TxDOT interchange (new or reconstructed) contract 81% complete, US 69, Jefferson County ($81,582,703, 17 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Williams Brothers Construction Co., INC. |
| Subcontractors | Long Legacy Enterprises, LLC (0.02%); Ray's Threading And Fab Shop (0.15%); (Inactive)mesa Rod Busters, INC. (4.91%); American Remediation Options, INC. (1.52%); Batterson, LLP (0.33%); Bortunco (0.58%); Buyers Barricades Houston, LLC (0.16%); Highway Pavement Specialties, INC. (0.16%); Scott Derr Painting Co, LLC (0.04%); Traffic Systems Construction, INC. (1.83%); Structural Integrity Group LLC (0.02%); Trp Construction Group, LLC (0.58%); A-Core Concrete Cutting Of Texas, INC. (0.01%); Sk Concrete Services LLC (0.32%); Texas Maintenance And Construction LLC (0.15%); Cross Plus Construction, LLC (0.12%); Sweeping Corporation Of America, LLC (0.17%) |
| Progress | 80.81% complete, 96.64% of time used |
| Amount | $81,582,703 revised (original $70,021,319) |
| Change orders | $11,561,385 |
| Paid to date | $65,925,182 |
| Work | Interchange (New Or Reconstructed) |
| Location | US 69, AT SH 73 to ., Jefferson County, Beaumont District |
| Let / began | 2021-09-02 / 2021-11-03 |
| Latest estimate | 2026-10-01 |
| Contract number | 9213202 |

## Why this score
- Contract over $10M.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.