# Williams Brothers Construction Co., INC.: TxDOT widen freeway contract 34% complete, IH 69, Harris County ($713,543,247, 32 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Williams Brothers Construction Co., INC. |
| Subcontractors | C & B Rebar Construction, INC. (0.04%); Steel Rain Construction & Logistics LLC (0.01%); Base Construction L.L.P. (5.36%); Sk Concrete Services LLC (0.04%); Peltier Brothers Construction, LLC (7.22%); Allstate Signal & Construction, LLC (1.74%); Buyers Barricades Houston, LLC (0.01%); Southwest Road & Safety Contractors, LTD. (0.37%); Trp Construction Group, LLC (0.25%); Rise Collective LLC (0.26%); Pfeiffer & Son LTD. (0.54%); Keller North America, INC. (0.27%); Kingz Industrial LLC (1%); (Inactive)mesa Rod Busters, INC. (3.76%); Roadway Construction, INC. (1.7%); Quality Turf Farms, L.C. (0.1%); Scott Derr Painting Co, LLC (0.01%); 1 Priority Environmental Services, LLC (0.35%); Taylor Contracting LLC (0.18%); Harper Brothers Construction LLC (5.88%); Mphs, INC. (0.25%); Sides Mechanical INC (0.06%); Flores Construction & Masonry LLC (0.01%); Texas Industrial Control Manufacturing LLC (0.04%); O. S. Interior Systems, INC. (0.02%); Kirtley Roofing & Sheet Metal, LLC (0.01%); Mickie Service, INC. (0.01%); Ckw Plumbing, INC. (0.01%); Axis Masonry & Stucco LLC (0.03%); Meb Concrete LLC (0.04%); Schnabel Foundation Company (0.69%); Hb Trenchless LLC (2.06%) |
| Progress | 34.18% complete, 20.8% of time used |
| Amount | $713,543,247 revised (original $695,529,456) |
| Change orders | $12,893,789 |
| Paid to date | $242,157,246 |
| Work | Widen Freeway |
| Location | IH 69, SH 288 to IH 45, Harris County, Houston District |
| Let / began | 2024-09-05 / 2025-01-08 |
| Latest estimate | 2026-09-30 |
| Contract number | 9243001 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.