# Yellowstone Landscape - Central, INC.: TxDOT landscape & scenic enhancement contract 99% complete, US 290, Waller County ($3,390,421)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Yellowstone Landscape - Central, INC. |
| Progress | 98.54% complete, 90% of time used |
| Amount | $3,390,421 revised (original $3,145,019) |
| Change orders | $245,398 |
| Paid to date | $3,340,767 |
| Work | Landscape & Scenic Enhancement |
| Location | US 290, BLASINGAME/OLD HOWTH RD (W OF SH 6) to WALLER/HARRIS COUNTY LINE, Waller County, Houston District |
| Let / began | 2021-11-04 / 2023-04-03 |
| Latest estimate | 2026-09-30 |
| Contract number | 11213222 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.