# Yunex LLC: TxDOT traffic signal contract 83% complete, SL 12, Dallas County ($2,619,055, 8 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Yunex LLC |
| Subcontractors | USA Amtech, INC. (5.17%); Ransom Drilling Services, LLC (1.63%); Jr West Texas Concrete LLC (13.66%); Medellin Hdd LLC (1.59%); Trp Construction Group, LLC (1.35%); Fc Traffic Control, INC. (0.89%); Molina Directional Drilling, LLC (0.75%); Peachtree Construction, LTD. (3.42%) |
| Progress | 82.92% complete, 128.14% of time used |
| Amount | $2,619,055 revised (original $2,415,555) |
| Paid to date | $2,003,022 |
| Work | Traffic Signal |
| Location | SL 12, NORTH OF MADDOX ROAD to HILLBURN DRIVE, Dallas County, Dallas District |
| Let / began | 2025-04-04 / 2025-08-29 |
| Latest estimate | 2026-10-01 |
| Contract number | 4253217 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.