# Zachry Construction Corporation: TxDOT widen non-freeway contract 100%+ complete, FM 1417, Grayson County ($34,434,371, 28 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Zachry Construction Corporation |
| Subcontractors | Scott Derr Painting Co, LLC (0.06%); Elite Asphalt, L.L.C. (0.51%); Toro Bravo Construction, LLC (0.02%); A. E. Moore Construction, INC. (0.39%); Circle H Boring, LLC (0.08%); W.O.E. Construction, INC. (0.28%); Highway Pavement Specialties, INC. (0.01%); Wylie Drilling & Drainage, INC. (0.41%); (Inactive)royal Rebar (0.79%); Panola Sign & Barricade, INC. (0.06%); Farr Foundation, INC. (1.08%); North Texas Contracting, INC. (18.97%); Rpm Xconstruction, LLC (4.06%); Premier Paving, LTD. (8.93%); Withers Construction, LLC (0.1%); Vista Ridge Concrete Pumping, INC. (0.04%); Coronado R. Construction, LLC (0.53%); Herdez Trucking, INC. (2.26%); Penhall Company (0.03%); North Texas Traffic Systems Construction (3.68%); (Inactive)inlet Structure Specialties, LTD. (0%); Act Saw Cutting & Removal (0.27%); Reynolds Asphalt & Construction Company (6.2%); H Torres Trucking, L.L.C. (1.26%); Trp Construction Group, LLC (0.44%); Good Earth Corporation (0.12%); Southern Cross Contractors, LLC (0.1%); Southeast Grinding And Grooving LLC (0.01%) |
| Progress | 102.16% complete, 99.5% of time used |
| Amount | $34,434,371 revised (original $31,389,823) |
| Change orders | $2,911,148 |
| Paid to date | $35,042,032 |
| Work | Widen Non-Freeway |
| Location | FM 1417, FM 1417 FROM 82 TO TAYLOR STREET, Grayson County, Paris District |
| Let / began | 2019-11-06 / 2020-02-25 |
| Latest estimate | 2026-10-05 |
| Contract number | 11193202 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.