# Zachry Construction Corporation: TxDOT upgrade to standards freeway contract 75% complete, IH 20, Parker County ($101,436,184, 30 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Zachry Construction Corporation |
| Subcontractors | USA Swppp Inspections, INC. (0.22%); Bortunco (1.23%); Brenda Price Trucking, INC. (0.68%); Antigo Construction, INC. (0.12%); Avanza Construction & Earthworks, LLC (0.41%); Layfield Construction, INC. (0.28%); Elite Striping, LLC (0.03%); 5 G Trucking & Hauling, LLC (0.22%); Q. Roberts Trucking Incorporated (0.6%); Imt Construction, LLC (0.25%); H Torres Trucking, L.L.C. (0.2%); Je Casey, LLC (0.15%); Coppell Construction Co., INC. (0.02%); Fga Construction LLC (1.91%); Cyclone Services LLC (0.01%); Vista Ridge Concrete Pumping, INC. (0.01%); Trp Construction Group, LLC (0.9%); Scott Derr Painting Co, LLC (0.01%); Oscar Orduno, INC. (1.24%); Mica Corporation (6.83%); Kiewit Infrastructure South Co. (23.5%); Act Saw Cutting & Removal (0.12%); A Brothers Milling, LLC (0.56%); Hermanos Steel, LLC (2.3%); Breda Company, INC. (0.01%); Durable Specialties, INC. (0.41%); King George Traffic Solutions LLC (0.81%); Texas Environmental Management - San Antonio, INC. (0.78%); American Concrete Trucking, LLC (0%); Dustrol, INC. (0.16%) |
| Progress | 75.36% complete, 62.26% of time used |
| Amount | $101,436,184 revised (original $98,670,164) |
| Change orders | $759,520 |
| Paid to date | $74,931,292 |
| Work | Upgrade To Standards Freeway |
| Location | IH 20, FM 1187/3325 to IH 20/30 SPLIT, Parker County, Fort Worth District |
| Let / began | 2024-05-03 / 2024-09-25 |
| Latest estimate | 2026-10-06 |
| Contract number | 5243202 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.