# Zachry Construction Corporation: TxDOT interchange (new or reconstructed) contract 35% complete, IH 35E, Denton County ($125,019,776, 23 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Zachry Construction Corporation |
| Subcontractors | Stripe-A-Zone, LLC (0.54%); Buyers Barricades, INC. (0.14%); Ancortex, INC. (4.31%); Cyclone Services LLC (0.06%); Hermanos Steel, LLC (0.06%); Act Saw Cutting & Removal (0.17%); Imt Construction, LLC (0.07%); Albatross Construction LLC (3.51%); Antigo Construction, INC. (0.05%); Scott Derr Painting Co, LLC (0.12%); Texop Construction (0.46%); Je Casey, LLC (0.1%); Texas Environmental Management - San Antonio, INC. (0.79%); Chiron Communication Services, LLC (0%); Royal Rebar INC (3.79%); A R Daniel Construction Services, Incorporated (0.76%); Sk Concrete Services LLC (0.03%); Synergy Signs & Services LLC (0.11%); American Fence Company, INC. (0.01%); Jagoe-Public Company (7.85%); Avanza Construction & Earthworks, LLC (4.58%); 5-04u, LLC (0.05%); Fga Construction LLC (2.21%) |
| Progress | 35.22% complete, 21.71% of time used |
| Amount | $125,019,776 revised (original $123,539,232) |
| Change orders | $-18,450 |
| Paid to date | $43,506,411 |
| Work | Interchange (New Or Reconstructed) |
| Location | IH 35E, SOUTH OF MAYHILL ROAD to SOUTH OF SL 288, Denton County, Dallas District |
| Let / began | 2025-06-05 / 2026-01-05 |
| Latest estimate | 2026-10-02 |
| Contract number | 6253202 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.