# Zachry Construction Corporation: TxDOT widen freeway contract 59% complete, IH 30, Tarrant County ($270,949,006, 31 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Zachry Construction Corporation |
| Subcontractors | A R Daniel Construction Services, Incorporated (1.11%); Imt Construction, LLC (0.87%); Act Saw Cutting & Removal (0.22%); Vista Ridge Concrete Pumping, INC. (0.07%); Texas Shafts, INC. (0.86%); Houston Sawing & Drilling (0.03%); Bulldog Services, LLC (0.02%); 5-04u, LLC (0.02%); Antigo Construction, INC. (0.06%); Texop Construction (0.12%); Hermanos Steel, LLC (0.82%); Mica Corporation (3.09%); Reynolds Asphalt & Construction Company (7.25%); (Inactive)royal Rebar (0.54%); Southeast Grinding And Grooving LLC (0.06%); Ancortex, INC. (3.16%); Fga Construction LLC (2.35%); Durable Specialties, INC. (0.13%); North Texas Contracting, INC. (2.18%); Buyers Barricades, INC. (0.04%); Freight Operation Services, LLC, DBA Fos Brokerage Services (0.55%); Texas Environmental Management - San Antonio, INC. (0.29%); A Brothers Milling, LLC (0.13%); West Texas Rock Resources, LLC (0%); Southern Cross Contractors, LLC (0.48%); Alliance Geotechnical Group, INC. (0.18%); Trp Construction Group, LLC (0.7%); D D M Construction Corporation (0.87%); H Torres Trucking, L.L.C. (0.04%); Circle H Boring, LLC (0.22%); A & A Sawing LLC (0.04%) |
| Progress | 58.82% complete, 33.23% of time used |
| Amount | $270,949,006 revised (original $267,014,970) |
| Change orders | $2,934,416 |
| Paid to date | $158,777,015 |
| Work | Widen Freeway |
| Location | IH 30, LINKCREST DRIVE to IH 820, Tarrant County, Fort Worth District |
| Let / began | 2024-07-09 / 2024-11-19 |
| Latest estimate | 2026-10-06 |
| Contract number | 7243001 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.