# Zachry Construction Corporation: TxDOT widen freeway contract 65% complete, IH 410, Bexar County ($84,602,028, 30 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Zachry Construction Corporation |
| Subcontractors | Valor Crane & Equipment LLC (0.04%); Guerra Underground LLC (2.07%); Primate Construction, LP (0.12%); Roadway Construction, INC. (1.56%); Environmental Safety Services, INC. (0.83%); Tnt Crane & Rigging, INC. (0.4%); Texas Cutting & Coring Gp, INC. (0.16%); Royal Rebar INC (2.32%); Z & L Concrete Contractors, INC. (1.69%); Aggregate Technologies, INC. (0.34%); Lone Star Paving Company (5.34%); Antigo Construction, INC. (0.04%); Beaird Drilling Services, INC. (1.99%); Bobcat Trucking, INC. (1.05%); Buyers Barricades San Antonio, LLC (0.17%); Jandy Group, LLC (0.12%); The Levy Company, INC. (4.3%); Trp Construction Group, LLC (0.46%); Williams Road, LLC (0.31%); Hh&W Transport INC (0.03%); Comal Aggregate LLC (0.36%); Fibertel, LLC (0.28%); Eggemeyer Land Clearing, LLC (0.01%); Texas Auger Boring LLC (0%); A K Fuquay Construction (0.27%); Panther Creek Transportation, INC. (1.11%); Choctaw Erectors, INC. (2.36%); Mtam Corporation (0.06%); Rucoba & Maya Construction, LLC (0.23%); Southeast Grinding And Grooving LLC (0.15%) |
| Progress | 65.17% complete, 32.61% of time used |
| Amount | $84,602,028 revised (original $84,474,579) |
| Change orders | $126,449 |
| Paid to date | $55,134,687 |
| Work | Widen Freeway |
| Location | IH 410, IH 35/IH 410 S INTERCHANGE to FM 78, Bexar County, San Antonio District |
| Let / began | 2024-08-02 / 2025-10-06 |
| Latest estimate | 2026-10-06 |
| Contract number | 8243253 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.