# Zack Burkett Co.: TxDOT widen non-freeway contract 22% complete, US 83, Cottle County ($49,253,082, 6 subs)

**Score:** 75/100

| Field | Value |
|---|---|
| Prime contractor | Zack Burkett Co. |
| Subcontractors | Dustrol, INC. (0.5%); Hjc Farms, INC. (2.17%); W. S. Construction Company (5.24%); Wolfe Construction Group, Incorporated (0.12%); Trp Construction Group, LLC (2.45%); Contractors Service, LTD. (0.26%) |
| Progress | 22.24% complete, 24.56% of time used |
| Amount | $49,253,082 revised (original $46,493,743) |
| Change orders | $2,759,339 |
| Paid to date | $10,951,688 |
| Work | Widen Non-Freeway |
| Location | US 83, FM 1038, SOUTH to KING C/L, Cottle County, Childress District |
| Let / began | 2026-01-06 / 2026-03-24 |
| Latest estimate | 2026-10-05 |
| Contract number | 1263001 |

## Why this score
- Contract over $10M.
- Under 25% complete: most materials and sub work still ahead.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.