# Zack Burkett Co.: TxDOT widen non-freeway contract 52% complete, FM 104, Cottle County ($6,279,570, 7 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Zack Burkett Co. |
| Subcontractors | W. S. Construction Company (3.69%); Trp Construction Group, LLC (2.16%); Wolfe Construction Group, Incorporated (0.55%); Contractors Service, LTD. (0.54%); Dustrol, INC. (1.12%); Apollo Constructors, INC. (0.59%); Hjc Farms, INC. (5.02%) |
| Progress | 51.77% complete, 50.91% of time used |
| Amount | $6,279,570 revised (original $6,279,570) |
| Paid to date | $3,250,726 |
| Work | Widen Non-Freeway |
| Location | FM 104, US 70, NORTH to 10 MILES, Cottle County, Childress District |
| Let / began | 2026-01-07 / 2026-06-30 |
| Latest estimate | 2026-10-05 |
| Contract number | 1263230 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.