# Zack Burkett Co.: TxDOT rehabilitation of existing road contract 83% complete, SH 6, Foard County ($6,898,953, 5 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Zack Burkett Co. |
| Subcontractors | Hjc Farms, INC. (8.87%); Fc Traffic Control, INC. (0.16%); Trp Construction Group, LLC (5.16%); Wolfe Construction Group, Incorporated (0.59%); Coppell Construction Co., INC. (1.44%) |
| Progress | 82.81% complete, 28.1% of time used |
| Amount | $6,898,953 revised (original $6,793,699) |
| Change orders | $105,255 |
| Paid to date | $5,713,132 |
| Work | Rehabilitation Of Existing Road |
| Location | SH 6, US 70, SOUTH to KNOX C/L, Foard County, Childress District |
| Let / began | 2026-02-05 / 2026-07-27 |
| Latest estimate | 2026-10-05 |
| Contract number | 2263210 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.