# Zack Burkett Co.: TxDOT widen non-freeway contract 100%+ complete, SH 240, Wichita County ($5,662,321, 7 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Zack Burkett Co. |
| Subcontractors | Texas Traffic And Barricade, LLC (0.36%); Dustrol, INC. (0.34%); W. S. Construction Company (14.6%); Hjc Farms, INC. (2.7%); Trp Construction Group, LLC (1.59%); Wolfe Construction Group, Incorporated (0.61%); (Inactive)site Barricades (0.23%) |
| Progress | 102.06% complete, 96.49% of time used |
| Amount | $5,662,321 revised (original $5,650,321) |
| Paid to date | $5,766,477 |
| Work | Widen Non-Freeway |
| Location | SH 240, FM 1813 to FM 369, Wichita County, Wichita Falls District |
| Let / began | 2025-05-01 / 2025-08-25 |
| Latest estimate | 2026-10-02 |
| Contract number | 5253007 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.