# Zack Burkett Co.: TxDOT restoration contract 97% complete, FM 422, Baylor County ($5,205,577, 6 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Zack Burkett Co. |
| Subcontractors | W. S. Construction Company (11.15%); Lanco Turf & Seeding, INC. (0.3%); Contractors Service, LTD. (3.04%); Murray Construction (0.69%); Dustrol, INC. (0.54%); Trp Construction Group, LLC (2.05%) |
| Progress | 96.73% complete, 88.1% of time used |
| Amount | $5,205,577 revised (original $5,191,085) |
| Change orders | $1,692 |
| Paid to date | $5,023,231 |
| Work | Restoration |
| Location | FM 422, STADIUM DRIVE to FM 1790, Baylor County, Wichita Falls District |
| Let / began | 2024-06-05 / 2024-08-30 |
| Latest estimate | 2026-10-01 |
| Contract number | 6243022 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.