# Zack Burkett Co.: TxDOT hazard elimination & safety contract 100% complete, FM 1287, Young County ($6,505,018, 5 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Zack Burkett Co. |
| Subcontractors | W. S. Construction Company (17.47%); Wolfe Construction Group, Incorporated (0.53%); Dustrol, INC. (0.36%); Hjc Farms, INC. (1.8%); Trp Construction Group, LLC (1.69%) |
| Progress | 99.69% complete, 70.98% of time used |
| Amount | $6,505,018 revised (original $6,394,018) |
| Change orders | $89,200 |
| Paid to date | $6,462,870 |
| Work | Hazard Elimination & Safety |
| Location | FM 1287, BRAZOS RIVER BRIDGE to 0.81 MI SOUTH OF BARRY LN, Young County, Wichita Falls District |
| Let / began | 2024-07-10 / 2024-11-13 |
| Latest estimate | 2026-10-01 |
| Contract number | 7243215 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.