# Zurich American Insurance Company: TxDOT widen freeway contract 86% complete, IH 10, Jefferson County ($136,562,374, 35 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Zurich American Insurance Company |
| Subcontractors | Antigo Construction, INC. (0.18%); Creacom, INC. (3.4%); (Inactive)hayward Baker, INC. (0.22%); Hemphill Wbe Pile Driving Co. (0.17%); Jb Pinnacle Group, LLC (1.03%); J.H. Painting Company (0.05%); Jmhp, INC. (0.88%); (Inactive)primate Construction, INC. (0.23%); Solis Trucking (0.6%); Southwest Road & Safety Contractors, LTD. (0.17%); Surface Preparation Technologies, LLC (0.02%); Texas Environmental Management - San Antonio, INC. (0.63%); W.W. Foundation Drilling, LTD. (1.08%); Plessala Trucking LLC (0.14%); Oveman Trucking, LLC (0.73%); Panther Creek Transportation, INC. (1.46%); Sb Fleet - Lube, LLC (1.66%); Buyers Barricades Houston, LLC (0.01%); Roadsafe Traffic Systems, INC. (0.44%); (Inactive)royal Rebar (0.85%); Hb Farmer Foundation, LLC (1.08%); Klp Commercial, L.L.C. (0.89%); Doran Steel, INC. (0.05%); Brister's Transport, LLC (0.52%); Ray's Threading And Fab Shop (0.41%); Heritage Materials, LLC (1.11%); Flasher Equipment Company (0.52%); Siboney Contracting Co. (0.73%); K. L. Durham Construction, L.L.C. (1.06%); Lindamood Demolition, INC. (0.43%); Mtam Corporation (0.05%); Batterson, LLP (0.8%); Schnabel Foundation Company (0.24%); Sweeping Corporation Of America, LLC (0.04%); Double A Underground LLC (0.41%) |
| Progress | 85.92% complete, 135.61% of time used |
| Amount | $136,562,374 revised (original $128,399,060) |
| Change orders | $8,163,315 |
| Paid to date | $117,329,392 |
| Work | Widen Freeway |
| Location | IH 10, FM 365, EAST to CR 131 (WALDEN ROAD), Jefferson County, Beaumont District |
| Let / began | 2018-07-11 / 2019-02-04 |
| Latest estimate | 2026-10-02 |
| Contract number | 7183201 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.