# J. Lee Milligan, INC.: apparent low bid $30,085,056 on TxDOT restoration job, US 87, Potter County (3 bidders)

**Score:** 65/100

| Field | Value |
|---|---|
| Low bidder | J. Lee Milligan, INC. |
| Low bid | $30,085,056 |
| Engineer's estimate | $26,383,174 |
| Vs estimate | 14% |
| Bidders | 3 |
| All bids | 1. J. Lee Milligan, INC. $30,085,056; 2. Rk Hall, LLC $30,964,796; 3. Gilvin-Terrill, LTD. $33,654,544 |
| Work | Restoration: Surfacing/Roadway Restoration |
| Location | US 87, AMARILLO CREEK to 11 TH STREET IN AMARILLO, Potter County, Amarillo District |
| Let date | 2026-08-06 |
| CSJ | 0041-07-121 |

## Why this score
- Low bid over $10M.
- Construction contract.

Source: Texas Department of Transportation bid tabulations (data.texas.gov) (https://data.texas.gov/d/de7b-7dna). Last refreshed: 2026-10-28T20:50:34.621Z.
From TxDOT bid tabulations. The apparent low bidder is not a final award: TxDOT may reject bids or award to another bidder. The engineer's estimate is TxDOT's published estimate total. Verify with TxDOT before relying on an award.