# Ratliff Hardscape, LTD.: apparent low bid $2,193,008 on TxDOT pedestrian, sidewalks & curb ramps job, Various, Tarrant County (7 bidders)

**Score:** 50/100

| Field | Value |
|---|---|
| Low bidder | Ratliff Hardscape, LTD. |
| Low bid | $2,193,008 |
| Engineer's estimate | $2,655,169 |
| Vs estimate | -17.4% |
| Bidders | 7 |
| All bids | 1. Ratliff Hardscape, LTD. $2,193,008; 2. Ti-Zack Concrete, LLC $2,358,485; 3. Castillo Aranda LLC $2,534,691; 6. Texas Steel Industrial Placing, LLC $3,079,682; 7. Ed Bell Construction Company $3,080,000 |
| Work | Pedestrian, Sidewalks & Curb Ramps: Bicycle And Pedestrian Improvements |
| Location | Various, Fort Worth District to City of Weatherford, Tarrant County, Fort Worth District |
| Let date | 2026-08-05 |
| CSJ | 0902-00-336 |

## Why this score
- Low bid over $1M.
- Construction contract.

Source: Texas Department of Transportation bid tabulations (data.texas.gov) (https://data.texas.gov/d/de7b-7dna). Last refreshed: 2026-11-04T21:51:10.085Z.
From TxDOT bid tabulations. The apparent low bidder is not a final award: TxDOT may reject bids or award to another bidder. The engineer's estimate is TxDOT's published estimate total. Verify with TxDOT before relying on an award.