# Mcgregor Door & Hardware LLC: sub to Gencap Construction Corp, $44,055 on "Covington PW Maintenance Facility" for City of Covington, Covington

**Score:** 30/100

| Field | Value |
|---|---|
| Company | Mcgregor Door & Hardware LLC |
| Role | Subcontractor |
| Hired by | Gencap Construction Corp |
| Agency | City of Covington (City or town) |
| Contract | Covington PW Maintenance Facility / 21507 |
| Project city | Covington |
| Company contract amount | $44,055 |
| Prime contract amount | $5,075,227 |
| Awarded | 2026-01-27 |
| Expected start | 2026-10-13 |
| Intent filed | 2026-10-15 |

## Why this score
- Contract of $25K or more.

Source: Washington State Department of Labor & Industries prevailing wage Statements of Intent (data.wa.gov) (https://data.wa.gov/d/t9je-9qwa). Last refreshed: 2026-11-04T06:09:51.453Z.
From Washington L&I prevailing wage Statements of Intent on data.wa.gov. Amounts and dates are as filed by the contractor; an intent records that work is planned under a public contract, not its completion or payment. Agency contacts and filings under personal names are excluded. Verify with L&I or the awarding agency.