[Research](/research) / TxDotContractProgressPulse

# Active TxDOT Contracts, Subcontractors & Percent Complete: 2026 statistics from 2,250 public records

**The most common progress is 25% to 75% complete: 800 of 2,250 records (35.6%) (as of 2026-10-28; source: Texas Department of Transportation construction contract recapitulation (data.texas.gov)).**

Data as of 2026-10-28 · Compiled by Zalwin from Texas Department of Transportation construction contract recapitulation (data.texas.gov) Copy citation

Work with the records behind these figures: all 2,250 TxDotContractProgressPulse records with source links, as one CSV.

Download all 2,250 records (CSV) — $4.99 → [Free sample: 3 records (CSV)](/v1/verticals/txdotcontractprogresspulse/records.csv) [Search the records free →](/v/txdotcontractprogresspulse?channel=pseo#vt-out)

Double opt-in: we send one confirmation email when digests start; nothing else until you confirm. One-click unsubscribe.

## Key findings

- Zalwin's TxDotContractProgressPulse dataset holds 2,250 TxDotContractProgressPulse records dated 2026-08-31 to 2026-10-12 (as of 2026-10-28; source: Texas Department of Transportation construction contract recapitulation (data.texas.gov)). [#](#finding-1)
- The most common progress is 25% to 75% complete: 800 of 2,250 records (35.6%) (as of 2026-10-28; source: Texas Department of Transportation construction contract recapitulation (data.texas.gov)). [#](#finding-2)
- Across 2,250 records with a stated contract amount, the total is $40,365,948,325 and the median is $1,878,859; the largest is $1,513,939,839 (Alamo Nex Construction, LLC) (as of 2026-10-28; source: Texas Department of Transportation construction contract recapitulation (data.texas.gov)). [#](#finding-3)
- The top 10% of records by contract amount (225 of 2,250) account for 79.8% of the total (as of 2026-10-28; source: Texas Department of Transportation construction contract recapitulation (data.texas.gov)). [#](#finding-4)
- 936 of 2,250 records (41.6%) are dated within the 30 days before 2026-10-28 (source: Texas Department of Transportation construction contract recapitulation (data.texas.gov)). [#](#finding-5)
- In Texas, the leading progress is 25% to 75% complete with 800 of 2,250 records (35.6%) (as of 2026-10-28; source: Texas Department of Transportation construction contract recapitulation (data.texas.gov)). [#](#finding-6)

## TxDotContractProgressPulse records by state

| Group | Records | Share | Total contract amount |
|---|---|---|---|
| Texas | 2,250 | 100.0% | $40,365,948,325 |

## TxDotContractProgressPulse records by progress

| Group | Records | Share | Total contract amount |
|---|---|---|---|
| 25% to 75% complete | 800 | 35.6% | $20,402,457,840 |
| 95%+ complete (closing out) | 751 | 33.4% | $9,473,027,530 |
| 75% to 95% complete | 448 | 19.9% | $7,968,112,013 |
| Under 25% complete | 251 | 11.2% | $2,522,350,941 |

## Methodology and data provenance

- Sample: 2,250 public records dated 2026-08-31 to 2026-10-12; illustrative samples excluded.

- Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov). Refreshed automatically about every 168 hours; figures above are as of 2026-10-28.

- Shares are of all records in the dataset; totals and medians use only records with a stated contract amount.

- Organization-level data only. Informational; verify individual records at the official source.

### Cite this study

Zalwin Research, "TxDotContractProgressPulse statistics" (data as of 2026-10-28), https://zalwin.com/research/txdotcontractprogresspulse