Research / TxDotContractProgressPulse
Active TxDOT Contracts, Subcontractors & Percent Complete: 2026 statistics from 2,250 public records
The most common progress is 25% to 75% complete: 800 of 2,250 records (35.6%) (as of 2026-10-28; source: Texas Department of Transportation construction contract recapitulation (data.texas.gov)).
Data as of · Compiled by Zalwin from Texas Department of Transportation construction contract recapitulation (data.texas.gov)
Key findings
- Zalwin's TxDotContractProgressPulse dataset holds 2,250 TxDotContractProgressPulse records dated 2026-08-31 to 2026-10-12 (as of 2026-10-28; source: Texas Department of Transportation construction contract recapitulation (data.texas.gov)). #
- The most common progress is 25% to 75% complete: 800 of 2,250 records (35.6%) (as of 2026-10-28; source: Texas Department of Transportation construction contract recapitulation (data.texas.gov)). #
- Across 2,250 records with a stated contract amount, the total is $40,365,948,325 and the median is $1,878,859; the largest is $1,513,939,839 (Alamo Nex Construction, LLC) (as of 2026-10-28; source: Texas Department of Transportation construction contract recapitulation (data.texas.gov)). #
- The top 10% of records by contract amount (225 of 2,250) account for 79.8% of the total (as of 2026-10-28; source: Texas Department of Transportation construction contract recapitulation (data.texas.gov)). #
- 936 of 2,250 records (41.6%) are dated within the 30 days before 2026-10-28 (source: Texas Department of Transportation construction contract recapitulation (data.texas.gov)). #
- In Texas, the leading progress is 25% to 75% complete with 800 of 2,250 records (35.6%) (as of 2026-10-28; source: Texas Department of Transportation construction contract recapitulation (data.texas.gov)). #
TxDotContractProgressPulse records by state
| Group | Records | Share | Total contract amount |
|---|---|---|---|
| Texas | 2,250 | 100.0% | $40,365,948,325 |
TxDotContractProgressPulse records by progress
| Group | Records | Share | Total contract amount |
|---|---|---|---|
| 25% to 75% complete | 800 | 35.6% | $20,402,457,840 |
| 95%+ complete (closing out) | 751 | 33.4% | $9,473,027,530 |
| 75% to 95% complete | 448 | 19.9% | $7,968,112,013 |
| Under 25% complete | 251 | 11.2% | $2,522,350,941 |
Methodology and data provenance
- Sample: 2,250 public records dated 2026-08-31 to 2026-10-12; illustrative samples excluded.
- Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov). Refreshed automatically about every 168 hours; figures above are as of 2026-10-28.
- Shares are of all records in the dataset; totals and medians use only records with a stated contract amount.
- Organization-level data only. Informational; verify individual records at the official source.
Cite this study
Zalwin Research, "TxDotContractProgressPulse statistics" (data as of 2026-10-28), https://zalwin.com/research/txdotcontractprogresspulse