James Construction Group, LLC's contract amount of $105,018,262 is 1.0x Longview Bridge And Road, LTD.'s $103,877,889 (96th percentile). James Construction Group, LLC is dated 2026-10-01; Longview Bridge And Road, LTD. 2026-10-05.
Data as of · Compiled by Zalwin from Texas Department of Transportation construction contract recapitulation (data.texas.gov)
Both records plus every comparable record, with all columns and source links · Card, Apple Pay, Google Pay or Link via Stripe
How does James Construction Group, LLC compare to Longview Bridge And Road, LTD.?
| Field | James Construction Group, LLC | Longview Bridge And Road, LTD. |
|---|---|---|
| Prime contractor | James Construction Group, LLC | Longview Bridge And Road, LTD. |
| Subcontractors | Allstate Signal & Construction, LLC (3.28%); Willow City Sign & Rail, INC. (0.73%); Stripe Lines, INC. (0.06%); J. T. B. Services, INC. (0.24%); Aviles Construction Service, INC (0.21%); Williams Road, LLC (0.91%); Vulcan Materials Asphalt And Construction, LLC (5.97%); Bls Services (0.08%); Valley Placers, LLC (0.19%); Who-B Trucking, INC. (3.35%); Durwood Greene Construction Co. (5.97%); J.Kru Land Services, LLC (0.01%); Professional Traffic Control LLC (0.7%); (Inactive)mesa Rod Busters, INC. (0.86%); Texas Environmental Management - San Antonio, INC. (1.4%); Southeast Grinding And Grooving LLC (0.07%); Curb Planet INC. (0.04%); Texas Sterling Construction Co. (2.19%); Sk Concrete Services LLC (0.27%) | (Inactive)blasters, INC. (0.01%); Antigo Construction, INC. (0.08%); (Inactive)carthage Drilling, INC. (0.01%); A R Daniel Construction Services, Incorporated (0.08%); Act Saw Cutting & Removal (0.02%); Time Striping, INC. (0.85%); Dustin Allen, INC. (0.63%); Hodges And Son Construction Company, INC. (0%); Collier-Manpower, INC. (0%); J. H. Oden Contracting Company (0.16%); Southwest Environment Services LLC (0.35%); Striping Technology, L.P. (2.47%); Toro Bravo Construction, LLC (0.01%); (Inactive)highway Intelligent Traffic Solutions, INC. (0.01%); Creative Design Concepts, INC. (0.04%); T & N Fence Construction (0.06%); Carthage Drilling, LLC (0.09%); Southeast Grinding And Grooving LLC (0.01%); Texop Construction (0.17%); Morris County Contractors, L.L.C. (0.17%); Kiteco Property Solutions INC. (0.21%); Surface Preparation Technologies, LLC (0.07%); Emery Sapp & Son's INC. (0.01%); Jb Pinnacle Group, LLC (0.03%) |
| Progress | 92.91% complete, 98.95% of time used | 83.87% complete, 92.75% of time used |
| Amount | $105,018,262 revised (original $107,298,495) | $103,877,889 revised (original $88,870,749) |
| Change orders | $-2,280,240 | $14,497,135 |
| Paid to date | $97,575,461 | $86,696,355 |
| Work | Widen Non-Freeway | Widen Freeway |
| Location | SH 105, FM 1484 to SAN JACINTO COUNTY LINE, Montgomery County, Houston District | IH 30, IH 30 to From: 0.6 MI W OF FM 989 To: ARKANSAS STATE LINE, Bowie County, Atlanta District |
| Let / began | 2022-10-06 / 2023-05-30 | 2020-05-08 / 2020-08-16 |
| Latest estimate | 2026-10-01 | 2026-10-05 |
| Contract number | 10223001 | 5203201 |
| contract amount percentile | 96th | 96th |
| Score | 55/100 | 65/100 |
| Peer rank and all 500 records (CSV) | 🔒 Click to unlock → | |
| Official source URLs for every peer record | 🔒 Click to unlock → | |
Official records: James Construction Group, LLC · Longview Bridge And Road, LTD.
Track TxDOT jobs in your work types
TxDotContractProgressPulse emails active TxDOT contracts matching your work types, progress stage and size as new pay estimates post.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.