Every TxDotContractProgressPulse record report, 200 per page, grouped by state. Records 1 to 200: (Inactive)highway Intelligent Traffic Solutions, INC.: TxDOT miscellaneous construction contract 100%+ complete, IH 45, Harris County ($3,549,691, 2 subs) to Deco Contractors, INC.: TxDOT rehabilitation of existing road contract 94% complete, IH 10, Harris County ($2,523,957, 1 sub). Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov).
Texas
- (Inactive)highway Intelligent Traffic Solutions, INC.: TxDOT miscellaneous construction contract 100%+ complete, IH 45, Harris County ($3,549,691, 2 subs)
- (Inactive)highway Intelligent Traffic Solutions, INC.: TxDOT miscellaneous construction contract 100%+ complete, VA, Tarrant County ($3,236,449, 5 subs)
- (Inactive)main Lane Industries LTD.: TxDOT bridge replacement contract 97% complete, FM 109, Colorado County ($7,071,020, 16 subs)
- (Inactive)ti-Zack Concrete, INC.: TxDOT miscellaneous construction contract 100%+ complete, SH 71, Wharton County ($3,090,207, 4 subs)
- *austin Traffic Signal Construction Co., INC.: TxDOT traffic signal contract 71% complete, SH 495, Hidalgo County ($3,525,673, 4 subs)
- *short-Line Corporation: TxDOT maintenance contract 100%+ complete, IH0030, Tarrant County ($13,234,683)
- *short-Line Corporation: TxDOT maintenance contract 95% complete, SH0046, Comal County ($7,673,218)
- 3lw Civil LLC: TxDOT hazard elimination & safety contract 80% complete, FM 855, Cherokee County ($4,139,164, 4 subs)
- 3lw Civil LLC: TxDOT maintenance contract 49% complete, IH0002, Hidalgo County ($2,807,402, 1 sub)
- 3lw Civil LLC: TxDOT miscellaneous construction contract 100% complete, BS 19J, Henderson County ($2,632,632, 6 subs)
- 3lw Civil LLC: TxDOT traffic signal contract 98% complete, US 83, Concho County ($14,993,516, 11 subs)
- A. K. Gillis & Sons, LLC: TxDOT hazard elimination & safety contract 77% complete, FM 1138, Collin County ($7,996,047, 11 subs)
- A. K. Gillis & Sons, LLC: TxDOT rehabilitation of existing road contract 90% complete, FM 547, Collin County ($17,299,208, 11 subs)
- A. K. Gillis & Sons, LLC: TxDOT rehabilitation of existing road contract 92% complete, FM 1487, Red River County ($6,973,581, 8 subs)
- A. K. Gillis & Sons, LLC: TxDOT rehabilitation of existing road contract 95% complete, FM 2120, Red River County ($9,932,732, 7 subs)
- A. K. Gillis & Sons, LLC: TxDOT rehabilitation of existing road contract 96% complete, FM 1743, Fannin County ($5,670,958, 6 subs)
- A. K. Gillis & Sons, LLC: TxDOT rehabilitation of existing road contract 99% complete, FM 2645, Fannin County ($7,652,012, 8 subs)
- A. L. Helmcamp, INC.: TxDOT bridge replacement contract 38% complete, FM 324, Angelina County ($27,453,785, 12 subs)
- A. L. Helmcamp, INC.: TxDOT bridge replacement contract 99% complete, SH 174, Hill County ($22,835,358, 13 subs)
- A. L. Helmcamp, INC.: TxDOT convert non-freeway to freeway contract 86% complete, IH 45, Freestone County ($38,708,859, 9 subs)
- A. L. Helmcamp, INC.: TxDOT hazard elimination & safety contract 25% complete, SH 243, Kaufman County ($3,600,112, 6 subs)
- A. L. Helmcamp, INC.: TxDOT hazard elimination & safety contract 42% complete, SH 198, Kaufman County ($5,472,211, 8 subs)
- A. L. Helmcamp, INC.: TxDOT miscellaneous construction contract 100%+ complete, VA, Palo Pinto County ($20,409,356, 12 subs)
- A. L. Helmcamp, INC.: TxDOT overlay contract 94% complete, US 84, Garza County ($13,430,032, 7 subs)
- A. L. Helmcamp, INC.: TxDOT rehabilitation of existing road contract 20% complete, US 70, Parmer County ($31,056,773, 10 subs)
- A. L. Helmcamp, INC.: TxDOT rehabilitation of existing road contract 27% complete, SH 137, Terry County ($22,831,736, 7 subs)
- A. L. Helmcamp, INC.: TxDOT rehabilitation of existing road contract 41% complete, FM 2727, Kaufman County ($17,212,280, 7 subs)
- A. L. Helmcamp, INC.: TxDOT rehabilitation of existing road contract 73% complete, US 87, Dawson County ($15,149,647, 8 subs)
- A. L. Helmcamp, INC.: TxDOT rehabilitation of existing road contract 93% complete, US 380, Jack County ($19,391,502, 8 subs)
- A. L. Helmcamp, INC.: TxDOT rehabilitation of existing road contract 96% complete, FM 2930, Navarro County ($13,089,489, 11 subs)
- A. L. Helmcamp, INC.: TxDOT rehabilitation of existing road contract 99% complete, FM 1450, Reeves County ($81,708,506, 9 subs)
- A. L. Helmcamp, INC.: TxDOT traffic protection devices contract 41% complete, US 84, Lamb County ($26,767,705, 10 subs)
- A. L. Helmcamp, INC.: TxDOT widen freeway contract 44% complete, US 82, Montague County ($40,029,127, 12 subs)
- A. L. Helmcamp, INC.: TxDOT widen non-freeway contract 19% complete, FM 2185, Culberson County ($123,817,484, 7 subs)
- A. L. Helmcamp, INC.: TxDOT widen non-freeway contract 35% complete, SH 36, Taylor County ($11,585,486, 11 subs)
- A. L. Helmcamp, INC.: TxDOT widen non-freeway contract 61% complete, SH 25, Wichita County ($20,591,832, 7 subs)
- A. L. Helmcamp, INC.: TxDOT widen non-freeway contract 64% complete, US 175, Cherokee County ($171,724,922, 15 subs)
- A. L. Helmcamp, INC.: TxDOT widen non-freeway contract 96% complete, FM 89, Taylor County ($25,387,138, 16 subs)
- Aaron Concrete Contractors, LLC: TxDOT hazard elimination & safety contract 26% complete, FM 3405, Williamson County ($2,927,951, 5 subs)
- Acme Bridge Company, INC.: TxDOT bridge replacement contract 53% complete, US 77, Lee County ($13,511,601, 14 subs)
- Acme Bridge Company, INC.: TxDOT bridge replacement contract 98% complete, SH 159, Fayette County ($4,352,983, 11 subs)
- Acme Bridge Company, INC.: TxDOT widen non-freeway contract 100%+ complete, RM 473, Kendall County ($4,459,611, 7 subs)
- Alamo Nex Construction, LLC: TxDOT widen freeway contract 85% complete, IH 35, Bexar County ($1,513,939,839)
- Allen Keller Company: TxDOT maintenance contract 37% complete, SH0130, Williamson County ($13,801,286, 3 subs)
- Allen Keller Company: TxDOT rehabilitation of existing road contract 44% complete, SH 29, Burnet County ($11,057,183, 5 subs)
- Allen Keller Company: TxDOT rehabilitation of existing road contract 46% complete, SH 16, San Saba County ($11,356,629, 7 subs)
- Allen Keller Company: TxDOT rehabilitation of existing road contract 82% complete, FM 45, Mills County ($32,777,188, 15 subs)
- Allstate Signal & Construction, LLC: TxDOT miscellaneous construction contract 100%+ complete, US 290, Harris County ($2,547,432, 5 subs)
- Allstate Signal & Construction, LLC: TxDOT traffic signal contract 77% complete, US 290, Waller County ($11,667,435, 2 subs)
- Altus Construction LLC: TxDOT bridge replacement contract 62% complete, US 70, Wilbarger County ($3,228,046, 5 subs)
- Altus Construction LLC: TxDOT bridge replacement contract 93% complete, SH 25, Archer County ($6,523,856, 9 subs)
- Altus Construction LLC: TxDOT bridge replacement contract 95% complete, IH 40, Carson County ($9,901,873, 10 subs)
- Altus Construction LLC: TxDOT grade crossing protection contract 100%+ complete, BI 20E, Midland County ($19,629,036, 10 subs)
- American Infrastructure Maintenance Management LLC: TxDOT maintenance contract 83% complete, Various, Ector County ($2,563,541)
- American Lighting And Signalization, LLC: TxDOT miscellaneous construction contract 40% complete, VA, Tarrant County ($4,315,755, 7 subs)
- American Lighting And Signalization, LLC: TxDOT traffic protection devices contract 74% complete, Various, Tom Green County ($2,922,081, 4 subs)
- American Lighting And Signalization, LLC: TxDOT traffic signal contract 10% complete, Various, Dallas County ($4,857,357, 4 subs)
- Anderson Columbia Co., INC.: TxDOT bridge widening or rehabilitation contract 75% complete, SH 255, Webb County ($25,298,244, 7 subs)
- Anderson Columbia Co., INC.: TxDOT convert non-freeway to freeway contract 69% complete, US 281, Jim Wells County ($140,487,953, 14 subs)
- Anderson Columbia Co., INC.: TxDOT convert non-freeway to freeway contract 74% complete, US 77, Kleberg County ($186,117,106, 19 subs)
- Anderson Columbia Co., INC.: TxDOT interchange (new or reconstructed) contract 100%+ complete, SH 35, Aransas County ($22,974,054, 13 subs)
- Anderson Columbia Co., INC.: TxDOT interchange (new or reconstructed) contract 39% complete, SL 20, Webb County ($50,601,761, 13 subs)
- Anderson Columbia Co., INC.: TxDOT interchange (new or reconstructed) contract 73% complete, FM 1472, Webb County ($4,125,144, 4 subs)
- Anderson Columbia Co., INC.: TxDOT miscellaneous construction contract 100%+ complete, VA, Hidalgo County ($30,805,925, 23 subs)
- Anderson Columbia Co., INC.: TxDOT miscellaneous construction contract 92% complete, IH 35, Webb County ($10,673,814, 7 subs)
- Anderson Columbia Co., INC.: TxDOT new location freeway contract 27% complete, US 77, Kleberg County ($178,365,453, 15 subs)
- Anderson Columbia Co., INC.: TxDOT overlay contract 100%+ complete, FM 2678, Refugio County ($13,952,404, 4 subs)
- Anderson Columbia Co., INC.: TxDOT overlay contract 82% complete, US 59, Webb County ($16,737,768, 5 subs)
- Anderson Columbia Co., INC.: TxDOT overlay contract 93% complete, FM 1069, San Patricio County ($2,503,581, 3 subs)
- Anderson Columbia Co., INC.: TxDOT rehabilitation of existing road contract 7% complete, SH 44, Webb County ($30,099,911, 9 subs)
- Anderson Columbia Co., INC.: TxDOT rehabilitation of existing road contract 8% complete, SH 16, Jim Hogg County ($5,580,787, 4 subs)
- Anderson Columbia Co., INC.: TxDOT widen freeway contract 100%+ complete, SH 141, Jim Wells County ($24,817,198, 9 subs)
- Anderson Columbia Co., INC.: TxDOT widen non-freeway contract 95% complete, SH 359, Webb County ($49,895,267, 11 subs)
- Apex Landscape & Irrigation, LLC: TxDOT landscape & scenic enhancement contract 95% complete, IH 35, Williamson County ($3,183,704, 2 subs)
- Aranda Brothers Construction Co., INC.: TxDOT bridge replacement contract 95% complete, CS, Harris County ($4,551,587, 3 subs)
- Arcosa Lws, LLC: TxDOT materials-only contract 35% complete, FM3063, Hardin County ($3,296,300)
- Asago, LLC: TxDOT rehabilitation of existing road contract 47% complete, FM 490, Willacy County ($5,129,329, 1 sub)
- Asago, LLC: TxDOT rehabilitation of existing road contract 98% complete, FM 1425, Hidalgo County ($14,586,887, 2 subs)
- Asago, LLC: TxDOT widen non-freeway contract 100%+ complete, FM 1925, Hidalgo County ($8,645,191, 4 subs)
- Atlantic Specialty Insurance Company: TxDOT hazard elimination & safety contract 100%+ complete, US 82, Grayson County ($7,613,816, 11 subs)
- Atlantic Specialty Insurance Company: TxDOT hazard elimination & safety contract 95% complete, IH 10, Crockett County ($5,149,375, 4 subs)
- Atlantic Specialty Insurance Company: TxDOT rehabilitation of existing road contract 81% complete, FM 1867, Dimmit County ($6,931,711, 9 subs)
- Austin Bridge & Road Services, LP: TxDOT interchange (new or reconstructed) contract 52% complete, IH 635, Dallas County ($548,189,139, 32 subs)
- Austin Bridge & Road Services, LP: TxDOT interchange (new or reconstructed) contract 77% complete, IH 30, Hunt County ($134,220,720, 27 subs)
- Austin Bridge & Road Services, LP: TxDOT maintenance contract 65% complete, IH0030, Tarrant County ($7,220,025)
- Austin Bridge & Road Services, LP: TxDOT rehabilitation of existing road contract 100% complete, SH 342, Ellis County ($5,619,051, 8 subs)
- Austin Bridge & Road Services, LP: TxDOT rehabilitation of existing road contract 100%+ complete, IH 20, Van Zandt County ($6,668,439, 8 subs)
- Austin Bridge & Road Services, LP: TxDOT rehabilitation of existing road contract 100%+ complete, SH 121, Tarrant County ($29,002,677, 17 subs)
- Austin Bridge & Road Services, LP: TxDOT rehabilitation of existing road contract 96% complete, FM 428, Collin County ($7,128,932, 11 subs)
- Austin Bridge & Road Services, LP: TxDOT upgrade to standards freeway contract 56% complete, US 175, Dallas County ($3,856,234, 12 subs)
- Austin Bridge & Road Services, LP: TxDOT widen freeway contract 100%+ complete, SH 151, Bexar County ($106,995,967, 28 subs)
- Austin Bridge & Road Services, LP: TxDOT widen freeway contract 53% complete, IH 35, Cooke County ($487,165,907, 32 subs)
- Austin Bridge & Road Services, LP: TxDOT widen freeway contract 98% complete, IH 35, Cooke County ($213,440,165, 44 subs)
- Baker & Company Construction, LLC: TxDOT hazard elimination & safety contract 23% complete, SH 34, Hunt County ($4,598,236, 8 subs)
- Baker & Company Construction, LLC: TxDOT hazard elimination & safety contract 69% complete, SH 37, Wood County ($4,103,741, 11 subs)
- Baker & Company Construction, LLC: TxDOT rehabilitation of existing road contract 100%+ complete, FM 1651, Van Zandt County ($11,020,766, 9 subs)
- Balfour Beatty Infrastructure, INC.: TxDOT widen freeway contract 22% complete, IH 30, Dallas County ($897,823,162, 28 subs)
- Balfour Beatty Infrastructure, INC.: TxDOT widen freeway contract 32% complete, IH 35, Travis County ($753,332,624, 39 subs)
- Big Creek Construction, LTD.: TxDOT bridge replacement contract 66% complete, SH 30, Grimes County ($12,568,401, 14 subs)
- Big Creek Construction, LTD.: TxDOT hazard elimination & safety contract 93% complete, US 183, Mills County ($4,574,425, 3 subs)
- Big Creek Construction, LTD.: TxDOT interchange (new or reconstructed) contract 80% complete, SH 9, Coryell County ($7,153,291, 7 subs)
- Big Creek Construction, LTD.: TxDOT interchange (new or reconstructed) contract 92% complete, SH 31, Mclennan County ($29,785,840, 16 subs)
- Big Creek Construction, LTD.: TxDOT maintenance contract 94% complete, IH0045, Madison County ($7,481,134)
- Big Creek Construction, LTD.: TxDOT maintenance contract 96% complete, FM1176, Brown County ($2,865,504)
- Big Creek Construction, LTD.: TxDOT overlay contract 100%+ complete, FM 279, Van Zandt County ($7,888,097, 11 subs)
- Big Creek Construction, LTD.: TxDOT rehabilitation of existing road contract 100% complete, FM 2113, Mclennan County ($10,864,735, 10 subs)
- Big Creek Construction, LTD.: TxDOT rehabilitation of existing road contract 21% complete, SH 159, Austin County ($12,747,743, 6 subs)
- Big Creek Construction, LTD.: TxDOT rehabilitation of existing road contract 30% complete, US, Lampasas County ($57,196,849, 10 subs)
- Big Creek Construction, LTD.: TxDOT rehabilitation of existing road contract 57% complete, FM 636, Navarro County ($6,208,367, 7 subs)
- Big Creek Construction, LTD.: TxDOT rehabilitation of existing road contract 79% complete, SH 7, Limestone County ($13,973,625, 8 subs)
- Big Creek Construction, LTD.: TxDOT rehabilitation of existing road contract 81% complete, FM 50, Robertson County ($20,736,867, 8 subs)
- Big Creek Construction, LTD.: TxDOT rehabilitation of existing road contract 96% complete, SH 34, Ellis County ($13,343,066, 9 subs)
- Big Creek Construction, LTD.: TxDOT rehabilitation of existing road contract 99% complete, FM 937, Robertson County ($8,561,397, 9 subs)
- Big Creek Construction, LTD.: TxDOT widen non-freeway contract 100%+ complete, FM 60, Burleson County ($35,354,638, 15 subs)
- Big Creek Construction, LTD.: TxDOT widen non-freeway contract 100%+ complete, SH 19, Henderson County ($14,745,378, 12 subs)
- Big Creek Construction, LTD.: TxDOT widen non-freeway contract 25% complete, SH 19, Van Zandt County ($11,228,661, 10 subs)
- Big Creek Construction, LTD.: TxDOT widen non-freeway contract 37% complete, SH 7, Leon County ($21,944,891, 8 subs)
- Big Creek Construction, LTD.: TxDOT widen non-freeway contract 98% complete, US 175, Anderson County ($59,553,583, 15 subs)
- Bk Field Operations LLC: TxDOT maintenance contract 25% complete, Various, Ector County ($2,667,137, 2 subs)
- Bk Field Operations LLC: TxDOT maintenance contract 56% complete, IH0035, Travis County ($2,550,242, 1 sub)
- Bontke Brothers Construction Company: TxDOT miscellaneous construction contract 86% complete, Various, Taylor County ($16,301,208, 7 subs)
- Bontke Brothers Construction Company: TxDOT widen non-freeway contract 51% complete, SH 153, Nolan County ($12,784,393, 4 subs)
- Brauntex Materials, INC.: TxDOT materials-only contract 30% complete, US0281, Blanco County ($2,556,199)
- Brazos Paving, INC.: TxDOT rehabilitation of existing road contract 99% complete, FM 159, Brazos County ($6,412,730, 7 subs)
- Brice Construction And Design LLC: TxDOT toll road contract 78% complete, SH 99, Harris County ($55,958,674, 25 subs)
- Brice Highway LLC: TxDOT bridge replacement contract 56% complete, CR, Liberty County ($5,682,863, 8 subs)
- Built Right Construction Of Oklahoma, LLC: TxDOT bridge widening or rehabilitation contract 100%+ complete, Various, Smith County ($3,363,832, 7 subs)
- Built Right Construction Of Oklahoma, LLC: TxDOT overlay contract 100%+ complete, IH 40, Carson County ($14,899,319, 15 subs)
- Built Right Construction Of Oklahoma, LLC: TxDOT remove hazardous paint (brg rehab) contract 68% complete, Various, Smith County ($8,553,979, 8 subs)
- C. E. Barker, LTD.: TxDOT bridge replacement contract 67% complete, SH 70, Nolan County ($7,106,676, 13 subs)
- C. E. Barker, LTD.: TxDOT miscellaneous construction contract 34% complete, SH 95, Bastrop County ($19,238,699, 10 subs)
- Callan Marine LTD: TxDOT maintenance contract 28% complete, SH0087, Galveston County ($16,470,001)
- Cekra INC.: TxDOT bridge widening or rehabilitation contract 100%+ complete, US 90, Colorado County ($7,589,905, 2 subs)
- Cen-Tex Irrigation Systems, INC.: TxDOT maintenance contract 30% complete, IH0035W, Johnson County ($5,571,033)
- Centerline Supply, INC.: TxDOT materials-only contract 68% complete, SH0031, Henderson County ($7,918,434)
- Centerline Technologies, LLC: TxDOT hazard elimination & safety contract 100%+ complete, Various, El Paso County ($3,099,449, 2 subs)
- Centerline Technologies, LLC: TxDOT materials-only contract 2% complete, SH0031, Henderson County ($4,044,059)
- Centerline Technologies, LLC: TxDOT traffic protection devices contract 100%+ complete, Various, El Paso County ($4,007,602, 2 subs)
- Central North Construction, LLC: TxDOT maintenance contract 77% complete, IH0030, Tarrant County ($2,822,996, 1 sub)
- Central North Construction, LLC: TxDOT maintenance contract 90% complete, IH0610, Harris County ($12,667,797, 2 subs)
- Ck Newberry, LLC: TxDOT hazard elimination & safety contract 30% complete, SH 16, Bexar County ($8,862,445, 7 subs)
- Ck Newberry, LLC: TxDOT overlay contract 100%+ complete, FM 57, Fisher County ($3,115,224, 2 subs)
- Ck Newberry, LLC: TxDOT overlay contract 100%+ complete, US 57, Maverick County ($16,976,678, 5 subs)
- Ck Newberry, LLC: TxDOT overlay contract 29% complete, US 180, Borden County ($7,878,044, 4 subs)
- Ck Newberry, LLC: TxDOT rehabilitation of existing road contract 100%+ complete, FM 1269, Scurry County ($5,865,546, 5 subs)
- Ck Newberry, LLC: TxDOT rehabilitation of existing road contract 100%+ complete, FM 887, Karnes County ($16,287,529, 10 subs)
- Ck Newberry, LLC: TxDOT rehabilitation of existing road contract 32% complete, SH 359, Jim Wells County ($15,560,651, 6 subs)
- Ck Newberry, LLC: TxDOT rehabilitation of existing road contract 54% complete, SH 255, Webb County ($26,369,665, 9 subs)
- Ck Newberry, LLC: TxDOT seal coat contract 96% complete, FM 313, Cameron County ($4,682,570, 3 subs)
- Ck Newberry, LLC: TxDOT seal coat contract 96% complete, SH 100, Cameron County ($6,401,217, 3 subs)
- Clark Construction Of Texas, INC.: TxDOT maintenance contract 100%+ complete, FM0394, Kerr County ($2,559,339)
- Clark Construction Of Texas, INC.: TxDOT rehabilitation of existing road contract 100%+ complete, SL 13, Bexar County ($6,133,808, 3 subs)
- Clark Construction Of Texas, INC.: TxDOT rehabilitation of existing road contract 76% complete, FM 3084, Calhoun County ($4,407,735, 6 subs)
- Clark Construction Of Texas, INC.: TxDOT rehabilitation of existing road contract 96% complete, FM 1301, Matagorda County ($7,128,161, 5 subs)
- Clark Construction Of Texas, INC.: TxDOT seal coat contract 72% complete, US 84, Freestone County ($22,830,766, 4 subs)
- Clark Construction Of Texas, INC.: TxDOT seal coat contract 81% complete, SH 7, Nacogdoches County ($9,466,576, 2 subs)
- Clark Construction Of Texas, INC.: TxDOT seal coat contract 83% complete, FM 1991, Bosque County ($5,528,014, 3 subs)
- Clark Construction Of Texas, INC.: TxDOT seal coat contract 85% complete, US 183, Stephens County ($4,300,701, 4 subs)
- Clark Construction Of Texas, INC.: TxDOT seal coat contract 86% complete, SH 31, Navarro County ($14,920,269, 5 subs)
- Clark Construction Of Texas, INC.: TxDOT seal coat contract 89% complete, UA 90, Colorado County ($20,881,905, 2 subs)
- Clark Construction Of Texas, INC.: TxDOT seal coat contract 89% complete, US 96, Jasper County ($13,469,049, 2 subs)
- Clark Construction Of Texas, INC.: TxDOT seal coat contract 91% complete, SH 24, Hunt County ($13,153,817, 4 subs)
- Continental Insurance Company (The): TxDOT widen non-freeway contract 99% complete, US 190, Bell County ($91,405,233, 33 subs)
- Copasa INC: TxDOT interchange (new or reconstructed) contract 99% complete, SL 360, Travis County ($81,044,812, 27 subs)
- Coppell Construction Co., INC.: TxDOT bridge replacement contract 100% complete, CR, Hamilton County ($4,204,973, 7 subs)
- Coppell Construction Co., INC.: TxDOT bridge replacement contract 70% complete, BI 27U, Hale County ($6,997,916, 11 subs)
- Cornerstone Paving And Construction, L.L.C.: TxDOT hazard elimination & safety contract 84% complete, US 190, Brazos County ($12,464,056, 10 subs)
- Cornerstone Paving And Construction, L.L.C.: TxDOT overlay contract 37% complete, US 90, Liberty County ($4,088,177, 5 subs)
- Cornerstone Paving And Construction, L.L.C.: TxDOT overlay contract 95% complete, BU 59S, Wharton County ($6,736,491, 5 subs)
- Cornerstone Paving And Construction, L.L.C.: TxDOT overlay contract 97% complete, SH 105, Liberty County ($2,780,143, 5 subs)
- Cornerstone Paving And Construction, L.L.C.: TxDOT widen non-freeway contract 95% complete, FM 256, Tyler County ($5,649,262, 6 subs)
- Cox Paving Of Texas, INC.: TxDOT seal coat contract 100%+ complete, SH 18, Winkler County ($13,615,793, 2 subs)
- Cox Paving Of Texas, INC.: TxDOT seal coat contract 85% complete, US 84, Mclennan County ($9,677,986, 2 subs)
- Cox Paving Of Texas, INC.: TxDOT seal coat contract 91% complete, FM 4, Johnson County ($3,000,138, 2 subs)
- D. I. J. Construction, INC.: TxDOT maintenance contract 15% complete, IH0035, Travis County ($2,475,274)
- D. I. J. Construction, INC.: TxDOT maintenance contract 80% complete, US0183, Brown County ($5,295,448)
- D. L. Lennon Incorporated - Contractor: TxDOT miscellaneous construction contract 100%+ complete, SH 11, Hunt County ($12,403,128, 11 subs)
- D. L. Lennon Incorporated - Contractor: TxDOT miscellaneous construction contract 26% complete, FM 1827, Collin County ($9,205,605, 10 subs)
- D. L. Lennon Incorporated - Contractor: TxDOT rehabilitation of existing road contract 100% complete, FM 271, Fannin County ($7,545,933, 9 subs)
- D. L. Lennon Incorporated - Contractor: TxDOT rehabilitation of existing road contract 100%+ complete, FM 121, Grayson County ($11,260,889, 8 subs)
- D. L. Lennon Incorporated - Contractor: TxDOT rehabilitation of existing road contract 44% complete, FM 1777, Collin County ($7,044,556, 10 subs)
- D. L. Lennon Incorporated - Contractor: TxDOT rehabilitation of existing road contract 49% complete, FM 1777, Collin County ($6,107,819, 10 subs)
- D. L. Lennon Incorporated - Contractor: TxDOT rehabilitation of existing road contract 61% complete, SH 78, Fannin County ($16,513,695, 8 subs)
- D. L. Lennon Incorporated - Contractor: TxDOT rehabilitation of existing road contract 98% complete, FM 68, Fannin County ($6,219,939, 8 subs)
- D. L. Lennon Incorporated - Contractor: TxDOT rehabilitation of existing road contract 99% complete, FM 512, Hunt County ($10,971,980, 11 subs)
- Dan Williams Company: TxDOT bridge replacement contract 100% complete, FM 3351, Comal County ($12,700,475, 7 subs)
- Dan Williams Company: TxDOT bridge replacement contract 100%+ complete, CS, El Paso County ($2,607,346, 3 subs)
- Dan Williams Company: TxDOT maintenance contract 100%+ complete, SH0191, Ector County ($3,953,358, 1 sub)
- Dan Williams Company: TxDOT maintenance contract 41% complete, FM1905, El Paso County ($2,576,383)
- Dan Williams Company: TxDOT rehabilitation of existing road contract 100%+ complete, SL 375, El Paso County ($8,103,436, 3 subs)
- Dan Williams Company: TxDOT traffic signal contract 100%+ complete, Various, Bexar County ($2,732,955, 2 subs)
- Dan Williams Company: TxDOT upgrade to standards freeway contract 66% complete, FM 812, Bastrop County ($7,716,777, 5 subs)
- Dan Williams Company: TxDOT widen non-freeway contract 53% complete, SS 320, El Paso County ($116,643,363, 9 subs)
- Dcc Construction And Services, L.L.C.: TxDOT bridge replacement contract 85% complete, CR, Polk County ($3,550,063, 6 subs)
- Dean Word Company, LTD.: TxDOT overlay contract 44% complete, FM 696, Bastrop County ($6,643,151, 6 subs)
- Dean Word Company, LTD.: TxDOT rehabilitation of existing road contract 100%+ complete, IH 10, Bexar County ($9,012,224, 8 subs)
- Dean Word Company, LTD.: TxDOT rehabilitation of existing road contract 61% complete, FM 2145, Fayette County ($5,765,058, 8 subs)
- Deco Contractors, INC.: TxDOT miscellaneous construction contract 100%+ complete, Various, Harris County ($3,999,107)
- Deco Contractors, INC.: TxDOT miscellaneous construction contract 89% complete, IH 69, Harris County ($6,961,069, 2 subs)
- Deco Contractors, INC.: TxDOT rehabilitation of existing road contract 94% complete, IH 10, Harris County ($2,523,957, 1 sub)